| Section 0001: ROADWAY ITEMS |
| Line | Item | Alt | Description | Bidder Data |
| 0010 | 203.0100 | | REMOVING SMALL PIPE CULVERTS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $765.00000 | 1.000 | EACH | | $765.00 |
| MCCABE CONSTRUCTION, INC. | $300.00000 | 1.000 | EACH | | $300.00 |
| HOFFMAN CONSTRUCTION COMPANY | $500.00000 | 1.000 | EACH | | $500.00 |
| JAMES CAPE AND SONS COMPANY | $500.00000 | 1.000 | EACH | | $500.00 |
| PEMBER COMPANIES, INC. | $959.93000 | 1.000 | EACH | | $959.93 |
| 0020 | 204.0100 | | REMOVING PAVEMENT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $4.70000 | 12,720.000 | SY | | $59,784.00 |
| MCCABE CONSTRUCTION, INC. | $3.50000 | 12,720.000 | SY | | $44,520.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.00000 | 12,720.000 | SY | | $38,160.00 |
| JAMES CAPE AND SONS COMPANY | $5.00000 | 12,720.000 | SY | | $63,600.00 |
| PEMBER COMPANIES, INC. | $3.39000 | 12,720.000 | SY | | $43,120.80 |
| 0030 | 204.0120 | | REMOVING ASPHALTIC SURFACE MILLING | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $4.50000 | 3,285.000 | SY | | $14,782.50 |
| MCCABE CONSTRUCTION, INC. | $2.59000 | 3,285.000 | SY | | $8,508.15 |
| HOFFMAN CONSTRUCTION COMPANY | $2.80000 | 3,285.000 | SY | | $9,198.00 |
| JAMES CAPE AND SONS COMPANY | $3.50000 | 3,285.000 | SY | | $11,497.50 |
| PEMBER COMPANIES, INC. | $2.21000 | 3,285.000 | SY | | $7,259.85 |
| 0040 | 204.0150 | | REMOVING CURB & GUTTER | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.80000 | 3,129.000 | LF | | $8,761.20 |
| MCCABE CONSTRUCTION, INC. | $3.00000 | 3,129.000 | LF | | $9,387.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.00000 | 3,129.000 | LF | | $9,387.00 |
| JAMES CAPE AND SONS COMPANY | $5.00000 | 3,129.000 | LF | | $15,645.00 |
| PEMBER COMPANIES, INC. | $2.94000 | 3,129.000 | LF | | $9,199.26 |
| 0050 | 204.0155 | | REMOVING CONCRETE SIDEWALK | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.80000 | 295.000 | SY | | $1,121.00 |
| MCCABE CONSTRUCTION, INC. | $4.00000 | 295.000 | SY | | $1,180.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.00000 | 295.000 | SY | | $885.00 |
| JAMES CAPE AND SONS COMPANY | $3.00000 | 295.000 | SY | | $885.00 |
| PEMBER COMPANIES, INC. | $5.56000 | 295.000 | SY | | $1,640.20 |
| 0060 | 204.0195 | | REMOVING CONCRETE BASES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $90.00000 | 22.000 | EACH | | $1,980.00 |
| MCCABE CONSTRUCTION, INC. | $100.00000 | 22.000 | EACH | | $2,200.00 |
| HOFFMAN CONSTRUCTION COMPANY | $66.00000 | 22.000 | EACH | | $1,452.00 |
| JAMES CAPE AND SONS COMPANY | $300.00000 | 22.000 | EACH | | $6,600.00 |
| PEMBER COMPANIES, INC. | $619.08000 | 22.000 | EACH | | $13,619.76 |
| 0070 | 204.0220 | | REMOVING INLETS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $225.00000 | 3.000 | EACH | | $675.00 |
| MCCABE CONSTRUCTION, INC. | $300.00000 | 3.000 | EACH | | $900.00 |
| HOFFMAN CONSTRUCTION COMPANY | $220.00000 | 3.000 | EACH | | $660.00 |
| JAMES CAPE AND SONS COMPANY | $500.00000 | 3.000 | EACH | | $1,500.00 |
| PEMBER COMPANIES, INC. | $580.08000 | 3.000 | EACH | | $1,740.24 |
| 0080 | 204.0245 | | REMOVING STORM SEWER (SIZE) 01. 12-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $17.00000 | 22.000 | LF | | $374.00 |
| MCCABE CONSTRUCTION, INC. | $15.00000 | 22.000 | LF | | $330.00 |
| HOFFMAN CONSTRUCTION COMPANY | $40.00000 | 22.000 | LF | | $880.00 |
| JAMES CAPE AND SONS COMPANY | $6.00000 | 22.000 | LF | | $132.00 |
| PEMBER COMPANIES, INC. | $30.96000 | 22.000 | LF | | $681.12 |
| 0090 | 204.9060.S | | REMOVING (ITEM DESCRIPTION) 01. CONCRETE CONTROL CABINET BASE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $250.00000 | 1.000 | EACH | | $250.00 |
| MCCABE CONSTRUCTION, INC. | $100.00000 | 1.000 | EACH | | $100.00 |
| HOFFMAN CONSTRUCTION COMPANY | $40.00000 | 1.000 | EACH | | $40.00 |
| JAMES CAPE AND SONS COMPANY | $500.00000 | 1.000 | EACH | | $500.00 |
| PEMBER COMPANIES, INC. | $926.52000 | 1.000 | EACH | | $926.52 |
| 0100 | 204.9105.S | | REMOVING (ITEM DESCRIPTION) 01. EXISTING SIGNALS AND LIGHTING | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $765.00000 | 1.000 | LS | | $765.00 |
| MCCABE CONSTRUCTION, INC. | $765.00000 | 1.000 | LS | | $765.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,200.00000 | 1.000 | LS | | $1,200.00 |
| JAMES CAPE AND SONS COMPANY | $765.00000 | 1.000 | LS | | $765.00 |
| PEMBER COMPANIES, INC. | $791.39000 | 1.000 | LS | | $791.39 |
| 0110 | 204.9105.S | | REMOVING (ITEM DESCRIPTION) 02. SIGN BRIDGE CANTILEVERED (STRUCTURE) | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2,500.00000 | 1.000 | LS | | $2,500.00 |
| MCCABE CONSTRUCTION, INC. | $2,500.00000 | 1.000 | LS | | $2,500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $2,500.00000 | 1.000 | LS | | $2,500.00 |
| JAMES CAPE AND SONS COMPANY | $2,500.00000 | 1.000 | LS | | $2,500.00 |
| PEMBER COMPANIES, INC. | $1,840.42000 | 1.000 | LS | | $1,840.42 |
| 0120 | 204.9105.S | | REMOVING (ITEM DESCRIPTION) 03. BILLBOARD SIGN | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $350.00000 | 1.000 | LS | | $350.00 |
| MCCABE CONSTRUCTION, INC. | $350.00000 | 1.000 | LS | | $350.00 |
| HOFFMAN CONSTRUCTION COMPANY | $440.00000 | 1.000 | LS | | $440.00 |
| JAMES CAPE AND SONS COMPANY | $350.00000 | 1.000 | LS | | $350.00 |
| PEMBER COMPANIES, INC. | $3,097.19000 | 1.000 | LS | | $3,097.19 |
| 0130 | 204.9180.S | | REMOVING (ITEM DESCRIPTION) 01. LOADING ZONE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $8.00000 | 194.000 | SY | | $1,552.00 |
| MCCABE CONSTRUCTION, INC. | $3.50000 | 194.000 | SY | | $679.00 |
| HOFFMAN CONSTRUCTION COMPANY | $5.00000 | 194.000 | SY | | $970.00 |
| JAMES CAPE AND SONS COMPANY | $3.00000 | 194.000 | SY | | $582.00 |
| PEMBER COMPANIES, INC. | $5.53000 | 194.000 | SY | | $1,072.82 |
| 0140 | 205.0100 | | EXCAVATION COMMON | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.70000 | 10,666.000 | CY | | $39,464.20 |
| MCCABE CONSTRUCTION, INC. | $7.90000 | 10,666.000 | CY | | $84,261.40 |
| HOFFMAN CONSTRUCTION COMPANY | $6.80000 | 10,666.000 | CY | | $72,528.80 |
| JAMES CAPE AND SONS COMPANY | $4.00000 | 10,666.000 | CY | | $42,664.00 |
| PEMBER COMPANIES, INC. | $6.39000 | 10,666.000 | CY | | $68,155.74 |
| 0150 | 208.0100 | | BORROW | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $8.65000 | 2,114.000 | CY | | $18,286.10 |
| MCCABE CONSTRUCTION, INC. | $5.50000 | 2,114.000 | CY | | $11,627.00 |
| HOFFMAN CONSTRUCTION COMPANY | $8.00000 | 2,114.000 | CY | | $16,912.00 |
| JAMES CAPE AND SONS COMPANY | $5.00000 | 2,114.000 | CY | | $10,570.00 |
| PEMBER COMPANIES, INC. | $8.19000 | 2,114.000 | CY | | $17,313.66 |
| 0160 | 211.0100 | | PREPARE FOUNDATION FOR ASPHALTIC PAVING (PROJECT) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2,500.00000 | 1.000 | LS | | $2,500.00 |
| MCCABE CONSTRUCTION, INC. | $4,000.00000 | 1.000 | LS | | $4,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,200.00000 | 1.000 | LS | | $1,200.00 |
| JAMES CAPE AND SONS COMPANY | $2,000.00000 | 1.000 | LS | | $2,000.00 |
| PEMBER COMPANIES, INC. | $9,590.95000 | 1.000 | LS | | $9,590.95 |
| 0170 | 213.0100 | | FINISHING ROADWAY (PROJECT) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $400.00000 | 1.000 | EACH | | $400.00 |
| MCCABE CONSTRUCTION, INC. | $6,125.00000 | 1.000 | EACH | | $6,125.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3,000.00000 | 1.000 | EACH | | $3,000.00 |
| JAMES CAPE AND SONS COMPANY | $2,000.00000 | 1.000 | EACH | | $2,000.00 |
| PEMBER COMPANIES, INC. | $6,395.03000 | 1.000 | EACH | | $6,395.03 |
| 0180 | 213.0100 | | FINISHING ROADWAY (PROJECT) 02. 8610-01-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $400.00000 | 1.000 | EACH | | $400.00 |
| MCCABE CONSTRUCTION, INC. | $6,125.00000 | 1.000 | EACH | | $6,125.00 |
| HOFFMAN CONSTRUCTION COMPANY | $2,000.00000 | 1.000 | EACH | | $2,000.00 |
| JAMES CAPE AND SONS COMPANY | $2,000.00000 | 1.000 | EACH | | $2,000.00 |
| PEMBER COMPANIES, INC. | $8,793.52000 | 1.000 | EACH | | $8,793.52 |
| 0190 | 305.0110 | | BASE AGGREGATE DENSE 3/4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $9.95000 | 665.000 | TON | | $6,616.75 |
| MCCABE CONSTRUCTION, INC. | $12.83000 | 665.000 | TON | | $8,531.95 |
| HOFFMAN CONSTRUCTION COMPANY | $10.00000 | 665.000 | TON | | $6,650.00 |
| JAMES CAPE AND SONS COMPANY | $8.75000 | 665.000 | TON | | $5,818.75 |
| PEMBER COMPANIES, INC. | $9.91000 | 665.000 | TON | | $6,590.15 |
| 0200 | 305.0120 | | BASE AGGREGATE DENSE 1 1/4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $8.35000 | 11,673.000 | TON | | $97,469.55 |
| MCCABE CONSTRUCTION, INC. | $8.29000 | 11,673.000 | TON | | $96,769.17 |
| HOFFMAN CONSTRUCTION COMPANY | $8.27000 | 11,673.000 | TON | | $96,535.71 |
| JAMES CAPE AND SONS COMPANY | $8.00000 | 11,673.000 | TON | | $93,384.00 |
| PEMBER COMPANIES, INC. | $9.54000 | 11,673.000 | TON | | $111,360.42 |
| 0210 | 305.0500 | | SHAPING SHOULDERS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $170.00000 | 29.000 | STA | | $4,930.00 |
| MCCABE CONSTRUCTION, INC. | $80.00000 | 29.000 | STA | | $2,320.00 |
| HOFFMAN CONSTRUCTION COMPANY | $30.00000 | 29.000 | STA | | $870.00 |
| JAMES CAPE AND SONS COMPANY | $100.00000 | 29.000 | STA | | $2,900.00 |
| PEMBER COMPANIES, INC. | $159.89000 | 29.000 | STA | | $4,636.81 |
| 0220 | 415.1090 | | CONCRETE PAVEMENT HES 9-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $28.00000 | 16,065.000 | SY | | $449,820.00 |
| MCCABE CONSTRUCTION, INC. | $28.00000 | 16,065.000 | SY | | $449,820.00 |
| HOFFMAN CONSTRUCTION COMPANY | $31.90000 | 16,065.000 | SY | | $512,473.50 |
| JAMES CAPE AND SONS COMPANY | $29.09000 | 16,065.000 | SY | | $467,330.85 |
| PEMBER COMPANIES, INC. | $31.83000 | 16,065.000 | SY | | $511,348.95 |
| 0230 | 415.1195.S | | QMP CONCRETE PAVEMENT URBAN | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,000.00000 | 5.000 | DAY | | $5,000.00 |
| MCCABE CONSTRUCTION, INC. | $1,000.00000 | 5.000 | DAY | | $5,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $845.00000 | 5.000 | DAY | | $4,225.00 |
| JAMES CAPE AND SONS COMPANY | $853.45000 | 5.000 | DAY | | $4,267.25 |
| PEMBER COMPANIES, INC. | $883.46000 | 5.000 | DAY | | $4,417.30 |
| 0240 | 415.2000.S | | INCENTIVE STRENGTH CONCRETE PAVEMENT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.00000 | 4,333.000 | DOL | | $4,333.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 4,333.000 | DOL | | $4,333.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 4,333.000 | DOL | | $4,333.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 4,333.000 | DOL | | $4,333.00 |
| PEMBER COMPANIES, INC. | $1.00000 | 4,333.000 | DOL | | $4,333.00 |
| 0250 | 416.0610 | | PAVEMENT TIES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $6.00000 | 276.000 | EACH | | $1,656.00 |
| MCCABE CONSTRUCTION, INC. | $6.00000 | 276.000 | EACH | | $1,656.00 |
| HOFFMAN CONSTRUCTION COMPANY | $8.00000 | 276.000 | EACH | | $2,208.00 |
| JAMES CAPE AND SONS COMPANY | $10.00000 | 276.000 | EACH | | $2,760.00 |
| PEMBER COMPANIES, INC. | $10.35000 | 276.000 | EACH | | $2,856.60 |
| 0260 | 416.0620 | | PAVEMENT DOWEL BARS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $10.00000 | 233.000 | EACH | | $2,330.00 |
| MCCABE CONSTRUCTION, INC. | $10.00000 | 233.000 | EACH | | $2,330.00 |
| HOFFMAN CONSTRUCTION COMPANY | $8.00000 | 233.000 | EACH | | $1,864.00 |
| JAMES CAPE AND SONS COMPANY | $12.00000 | 233.000 | EACH | | $2,796.00 |
| PEMBER COMPANIES, INC. | $12.41000 | 233.000 | EACH | | $2,891.53 |
| 0270 | 416.0805 | | CONCRETE PAVEMENT GAPS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $500.00000 | 2.000 | EACH | | $1,000.00 |
| MCCABE CONSTRUCTION, INC. | $500.00000 | 2.000 | EACH | | $1,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,500.00000 | 2.000 | EACH | | $3,000.00 |
| JAMES CAPE AND SONS COMPANY | $1,200.00000 | 2.000 | EACH | | $2,400.00 |
| PEMBER COMPANIES, INC. | $1,241.40000 | 2.000 | EACH | | $2,482.80 |
| 0280 | 455.0105 | | ASPHALTIC MATERIAL PG58-28 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $195.00000 | 30.500 | TON | | $5,947.50 |
| MCCABE CONSTRUCTION, INC. | $195.00000 | 30.500 | TON | | $5,947.50 |
| HOFFMAN CONSTRUCTION COMPANY | $195.00000 | 30.500 | TON | | $5,947.50 |
| JAMES CAPE AND SONS COMPANY | $195.00000 | 30.500 | TON | | $5,947.50 |
| PEMBER COMPANIES, INC. | $201.73000 | 30.500 | TON | | $6,152.77 |
| 0290 | 455.0115 | | ASPHALTIC MATERIAL PG64-22 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $195.00000 | 117.800 | TON | | $22,971.00 |
| MCCABE CONSTRUCTION, INC. | $195.00000 | 117.800 | TON | | $22,971.00 |
| HOFFMAN CONSTRUCTION COMPANY | $195.00000 | 117.800 | TON | | $22,971.00 |
| JAMES CAPE AND SONS COMPANY | $195.00000 | 117.800 | TON | | $22,971.00 |
| PEMBER COMPANIES, INC. | $201.73000 | 117.800 | TON | | $23,763.79 |
| 0300 | 455.0605 | | TACK COAT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $6.61000 | 298.000 | GAL | | $1,969.78 |
| MCCABE CONSTRUCTION, INC. | $6.61000 | 298.000 | GAL | | $1,969.78 |
| HOFFMAN CONSTRUCTION COMPANY | $6.61000 | 298.000 | GAL | | $1,969.78 |
| JAMES CAPE AND SONS COMPANY | $6.61000 | 298.000 | GAL | | $1,969.78 |
| PEMBER COMPANIES, INC. | $6.84000 | 298.000 | GAL | | $2,038.32 |
| 0310 | 460.1100 | | HMA PAVEMENT TYPE E-0.3 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $45.29000 | 431.000 | TON | | $19,519.99 |
| MCCABE CONSTRUCTION, INC. | $45.29000 | 431.000 | TON | | $19,519.99 |
| HOFFMAN CONSTRUCTION COMPANY | $45.29000 | 431.000 | TON | | $19,519.99 |
| JAMES CAPE AND SONS COMPANY | $45.29000 | 431.000 | TON | | $19,519.99 |
| PEMBER COMPANIES, INC. | $46.85000 | 431.000 | TON | | $20,192.35 |
| 0320 | 460.1110 | | HMA PAVEMENT TYPE E-10 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $54.09000 | 1,961.000 | TON | | $106,070.49 |
| MCCABE CONSTRUCTION, INC. | $54.09000 | 1,961.000 | TON | | $106,070.49 |
| HOFFMAN CONSTRUCTION COMPANY | $54.09000 | 1,961.000 | TON | | $106,070.49 |
| JAMES CAPE AND SONS COMPANY | $54.09000 | 1,961.000 | TON | | $106,070.49 |
| PEMBER COMPANIES, INC. | $55.96000 | 1,961.000 | TON | | $109,737.56 |
| 0330 | 460.3000 | | QMP HMA MIXTURE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.60000 | 2,469.000 | TON | | $6,419.40 |
| MCCABE CONSTRUCTION, INC. | $2.60000 | 2,469.000 | TON | | $6,419.40 |
| HOFFMAN CONSTRUCTION COMPANY | $2.60000 | 2,469.000 | TON | | $6,419.40 |
| JAMES CAPE AND SONS COMPANY | $2.60000 | 2,469.000 | TON | | $6,419.40 |
| PEMBER COMPANIES, INC. | $2.69000 | 2,469.000 | TON | | $6,641.61 |
| 0340 | 465.0125 | | ASPHALTIC SURFACE TEMPORARY | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $68.18000 | 635.000 | TON | | $43,294.30 |
| MCCABE CONSTRUCTION, INC. | $68.18000 | 635.000 | TON | | $43,294.30 |
| HOFFMAN CONSTRUCTION COMPANY | $68.18000 | 635.000 | TON | | $43,294.30 |
| JAMES CAPE AND SONS COMPANY | $68.18000 | 635.000 | TON | | $43,294.30 |
| PEMBER COMPANIES, INC. | $70.53000 | 635.000 | TON | | $44,786.55 |
| 0350 | 465.0315 | | ASPHALTIC FLUMES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $71.25000 | 21.000 | SY | | $1,496.25 |
| MCCABE CONSTRUCTION, INC. | $71.25000 | 21.000 | SY | | $1,496.25 |
| HOFFMAN CONSTRUCTION COMPANY | $71.25000 | 21.000 | SY | | $1,496.25 |
| JAMES CAPE AND SONS COMPANY | $71.25000 | 21.000 | SY | | $1,496.25 |
| PEMBER COMPANIES, INC. | $73.71000 | 21.000 | SY | | $1,547.91 |
| 0360 | 465.0400 | | ASPHALTIC SHOULDER RUMBLE STRIP | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.25000 | 2,344.000 | LF | | $2,930.00 |
| MCCABE CONSTRUCTION, INC. | $1.25000 | 2,344.000 | LF | | $2,930.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.60000 | 2,344.000 | LF | | $3,750.40 |
| JAMES CAPE AND SONS COMPANY | $1.25000 | 2,344.000 | LF | | $2,930.00 |
| PEMBER COMPANIES, INC. | $1.55000 | 2,344.000 | LF | | $3,633.20 |
| 0370 | 520.0324 | | CULVERT PIPE CLASS IV 24-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $38.00000 | 22.000 | LF | | $836.00 |
| MCCABE CONSTRUCTION, INC. | $43.00000 | 22.000 | LF | | $946.00 |
| HOFFMAN CONSTRUCTION COMPANY | $55.00000 | 22.000 | LF | | $1,210.00 |
| JAMES CAPE AND SONS COMPANY | $33.00000 | 22.000 | LF | | $726.00 |
| PEMBER COMPANIES, INC. | $44.30000 | 22.000 | LF | | $974.60 |
| 0380 | 520.7000 | | CLEANING CULVERT PIPES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $300.00000 | 3.000 | EACH | | $900.00 |
| MCCABE CONSTRUCTION, INC. | $350.00000 | 3.000 | EACH | | $1,050.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 3.000 | EACH | | $1,200.00 |
| JAMES CAPE AND SONS COMPANY | $350.00000 | 3.000 | EACH | | $1,050.00 |
| PEMBER COMPANIES, INC. | $321.00000 | 3.000 | EACH | | $963.00 |
| 0390 | 520.8000.S | | CULVERT PIPE CONCRETE COLLAR | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $150.00000 | 2.000 | EACH | | $300.00 |
| MCCABE CONSTRUCTION, INC. | $250.00000 | 2.000 | EACH | | $500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,200.00000 | 2.000 | EACH | | $2,400.00 |
| JAMES CAPE AND SONS COMPANY | $200.00000 | 2.000 | EACH | | $400.00 |
| PEMBER COMPANIES, INC. | $609.33000 | 2.000 | EACH | | $1,218.66 |
| 0400 | 522.0318 | | CULVERT PIPE REINFORCED CONCRETE CLASS IV 18-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $32.00000 | 120.000 | LF | | $3,840.00 |
| MCCABE CONSTRUCTION, INC. | $32.50000 | 120.000 | LF | | $3,900.00 |
| HOFFMAN CONSTRUCTION COMPANY | $55.00000 | 120.000 | LF | | $6,600.00 |
| JAMES CAPE AND SONS COMPANY | $34.00000 | 120.000 | LF | | $4,080.00 |
| PEMBER COMPANIES, INC. | $62.22000 | 120.000 | LF | | $7,466.40 |
| 0410 | 522.1015 | | APRON ENDWALLS FOR CULVERT PIPE REINFORCED CONCRETE 15-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $415.00000 | 3.000 | EACH | | $1,245.00 |
| MCCABE CONSTRUCTION, INC. | $375.00000 | 3.000 | EACH | | $1,125.00 |
| HOFFMAN CONSTRUCTION COMPANY | $220.00000 | 3.000 | EACH | | $660.00 |
| JAMES CAPE AND SONS COMPANY | $500.00000 | 3.000 | EACH | | $1,500.00 |
| PEMBER COMPANIES, INC. | $557.58000 | 3.000 | EACH | | $1,672.74 |
| 0420 | 522.1018 | | APRON ENDWALLS FOR CULVERT PIPE REINFORCED CONCRETE 18-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $440.00000 | 4.000 | EACH | | $1,760.00 |
| MCCABE CONSTRUCTION, INC. | $405.00000 | 4.000 | EACH | | $1,620.00 |
| HOFFMAN CONSTRUCTION COMPANY | $440.00000 | 4.000 | EACH | | $1,760.00 |
| JAMES CAPE AND SONS COMPANY | $600.00000 | 4.000 | EACH | | $2,400.00 |
| PEMBER COMPANIES, INC. | $587.31000 | 4.000 | EACH | | $2,349.24 |
| 0430 | 524.0624 | | APRON ENDWALLS FOR CULVERT PIPE SALVAGED 24-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $250.00000 | 1.000 | EACH | | $250.00 |
| MCCABE CONSTRUCTION, INC. | $130.00000 | 1.000 | EACH | | $130.00 |
| HOFFMAN CONSTRUCTION COMPANY | $380.00000 | 1.000 | EACH | | $380.00 |
| JAMES CAPE AND SONS COMPANY | $300.00000 | 1.000 | EACH | | $300.00 |
| PEMBER COMPANIES, INC. | $272.46000 | 1.000 | EACH | | $272.46 |
| 0440 | 601.0115 | | CONCRETE CURB TYPE G | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $12.00000 | 180.000 | LF | | $2,160.00 |
| MCCABE CONSTRUCTION, INC. | $12.00000 | 180.000 | LF | | $2,160.00 |
| HOFFMAN CONSTRUCTION COMPANY | $9.92000 | 180.000 | LF | | $1,785.60 |
| JAMES CAPE AND SONS COMPANY | $14.29000 | 180.000 | LF | | $2,572.20 |
| PEMBER COMPANIES, INC. | $14.78000 | 180.000 | LF | | $2,660.40 |
| 0450 | 601.0409 | | CONCRETE CURB & GUTTER 30-INCH TYPE A | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $15.00000 | 80.000 | LF | | $1,200.00 |
| MCCABE CONSTRUCTION, INC. | $15.00000 | 80.000 | LF | | $1,200.00 |
| HOFFMAN CONSTRUCTION COMPANY | $8.56000 | 80.000 | LF | | $684.80 |
| JAMES CAPE AND SONS COMPANY | $16.63000 | 80.000 | LF | | $1,330.40 |
| PEMBER COMPANIES, INC. | $17.20000 | 80.000 | LF | | $1,376.00 |
| 0460 | 601.0411 | | CONCRETE CURB & GUTTER 30-INCH TYPE D | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $12.00000 | 330.000 | LF | | $3,960.00 |
| MCCABE CONSTRUCTION, INC. | $12.00000 | 330.000 | LF | | $3,960.00 |
| HOFFMAN CONSTRUCTION COMPANY | $8.56000 | 330.000 | LF | | $2,824.80 |
| JAMES CAPE AND SONS COMPANY | $16.63000 | 330.000 | LF | | $5,487.90 |
| PEMBER COMPANIES, INC. | $17.20000 | 330.000 | LF | | $5,676.00 |
| 0470 | 601.0421 | | CONCRETE CURB & GUTTER 36-INCH TYPE A | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $10.00000 | 3,693.000 | LF | | $36,930.00 |
| MCCABE CONSTRUCTION, INC. | $10.00000 | 3,693.000 | LF | | $36,930.00 |
| HOFFMAN CONSTRUCTION COMPANY | $9.46000 | 3,693.000 | LF | | $34,935.78 |
| JAMES CAPE AND SONS COMPANY | $9.74000 | 3,693.000 | LF | | $35,969.82 |
| PEMBER COMPANIES, INC. | $10.08000 | 3,693.000 | LF | | $37,225.44 |
| 0480 | 601.0423 | | CONCRETE CURB & GUTTER 36-INCH TYPE D | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $12.00000 | 240.000 | LF | | $2,880.00 |
| MCCABE CONSTRUCTION, INC. | $12.00000 | 240.000 | LF | | $2,880.00 |
| HOFFMAN CONSTRUCTION COMPANY | $9.46000 | 240.000 | LF | | $2,270.40 |
| JAMES CAPE AND SONS COMPANY | $16.63000 | 240.000 | LF | | $3,991.20 |
| PEMBER COMPANIES, INC. | $17.20000 | 240.000 | LF | | $4,128.00 |
| 0490 | 602.0405 | | CONCRETE SIDEWALK 4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.50000 | 4,485.000 | SF | | $11,212.50 |
| MCCABE CONSTRUCTION, INC. | $2.50000 | 4,485.000 | SF | | $11,212.50 |
| HOFFMAN CONSTRUCTION COMPANY | $2.47000 | 4,485.000 | SF | | $11,077.95 |
| JAMES CAPE AND SONS COMPANY | $2.26000 | 4,485.000 | SF | | $10,136.10 |
| PEMBER COMPANIES, INC. | $2.34000 | 4,485.000 | SF | | $10,494.90 |
| 0500 | 602.0501.S | | CURB RAMP DETECTABLE WARNING FIELD | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $40.00000 | 96.000 | SF | | $3,840.00 |
| MCCABE CONSTRUCTION, INC. | $40.00000 | 96.000 | SF | | $3,840.00 |
| HOFFMAN CONSTRUCTION COMPANY | $40.00000 | 96.000 | SF | | $3,840.00 |
| JAMES CAPE AND SONS COMPANY | $30.00000 | 96.000 | SF | | $2,880.00 |
| PEMBER COMPANIES, INC. | $31.04000 | 96.000 | SF | | $2,979.84 |
| 0510 | 602.1000 | | CONCRETE LOADING ZONE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.50000 | 3,000.000 | SF | | $10,500.00 |
| MCCABE CONSTRUCTION, INC. | $3.50000 | 3,000.000 | SF | | $10,500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.35000 | 3,000.000 | SF | | $10,050.00 |
| JAMES CAPE AND SONS COMPANY | $3.48000 | 3,000.000 | SF | | $10,440.00 |
| PEMBER COMPANIES, INC. | $3.60000 | 3,000.000 | SF | | $10,800.00 |
| 0520 | 608.0312 | | STORM SEWER PIPE REINFORCED CONCRETE CLASS III 12-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $27.00000 | 476.000 | LF | | $12,852.00 |
| MCCABE CONSTRUCTION, INC. | $27.85000 | 476.000 | LF | | $13,256.60 |
| HOFFMAN CONSTRUCTION COMPANY | $26.00000 | 476.000 | LF | | $12,376.00 |
| JAMES CAPE AND SONS COMPANY | $19.55000 | 476.000 | LF | | $9,305.80 |
| PEMBER COMPANIES, INC. | $54.42000 | 476.000 | LF | | $25,903.92 |
| 0530 | 608.0315 | | STORM SEWER PIPE REINFORCED CONCRETE CLASS III 15-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $30.00000 | 232.000 | LF | | $6,960.00 |
| MCCABE CONSTRUCTION, INC. | $33.00000 | 232.000 | LF | | $7,656.00 |
| HOFFMAN CONSTRUCTION COMPANY | $32.00000 | 232.000 | LF | | $7,424.00 |
| JAMES CAPE AND SONS COMPANY | $23.00000 | 232.000 | LF | | $5,336.00 |
| PEMBER COMPANIES, INC. | $56.50000 | 232.000 | LF | | $13,108.00 |
| 0540 | 611.0301 | | INLETS TYPE 1 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $655.00000 | 4.000 | EACH | | $2,620.00 |
| MCCABE CONSTRUCTION, INC. | $665.00000 | 4.000 | EACH | | $2,660.00 |
| HOFFMAN CONSTRUCTION COMPANY | $700.00000 | 4.000 | EACH | | $2,800.00 |
| JAMES CAPE AND SONS COMPANY | $1,070.00000 | 4.000 | EACH | | $4,280.00 |
| PEMBER COMPANIES, INC. | $1,000.66000 | 4.000 | EACH | | $4,002.64 |
| 0550 | 611.0303 | | INLETS TYPE 3 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $670.00000 | 7.000 | EACH | | $4,690.00 |
| MCCABE CONSTRUCTION, INC. | $555.00000 | 7.000 | EACH | | $3,885.00 |
| HOFFMAN CONSTRUCTION COMPANY | $700.00000 | 7.000 | EACH | | $4,900.00 |
| JAMES CAPE AND SONS COMPANY | $950.00000 | 7.000 | EACH | | $6,650.00 |
| PEMBER COMPANIES, INC. | $764.95000 | 7.000 | EACH | | $5,354.65 |
| 0560 | 611.0305 | | INLETS TYPE 8 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,050.00000 | 3.000 | EACH | | $3,150.00 |
| MCCABE CONSTRUCTION, INC. | $1,335.00000 | 3.000 | EACH | | $4,005.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,500.00000 | 3.000 | EACH | | $4,500.00 |
| JAMES CAPE AND SONS COMPANY | $1,500.00000 | 3.000 | EACH | | $4,500.00 |
| PEMBER COMPANIES, INC. | $1,096.26000 | 3.000 | EACH | | $3,288.78 |
| 0570 | 611.0420 | | RECONSTRUCTING MANHOLES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $900.00000 | 1.000 | EACH | | $900.00 |
| MCCABE CONSTRUCTION, INC. | $525.00000 | 1.000 | EACH | | $525.00 |
| HOFFMAN CONSTRUCTION COMPANY | $800.00000 | 1.000 | EACH | | $800.00 |
| JAMES CAPE AND SONS COMPANY | $500.00000 | 1.000 | EACH | | $500.00 |
| PEMBER COMPANIES, INC. | $1,083.80000 | 1.000 | EACH | | $1,083.80 |
| 0580 | 611.0530 | | MANHOLE COVERS TYPE J | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $275.00000 | 1.000 | EACH | | $275.00 |
| MCCABE CONSTRUCTION, INC. | $275.00000 | 1.000 | EACH | | $275.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 1.000 | EACH | | $400.00 |
| JAMES CAPE AND SONS COMPANY | $300.00000 | 1.000 | EACH | | $300.00 |
| PEMBER COMPANIES, INC. | $236.96000 | 1.000 | EACH | | $236.96 |
| 0590 | 611.0612 | | INLET COVERS TYPE C | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $280.00000 | 2.000 | EACH | | $560.00 |
| MCCABE CONSTRUCTION, INC. | $277.00000 | 2.000 | EACH | | $554.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 2.000 | EACH | | $800.00 |
| JAMES CAPE AND SONS COMPANY | $300.00000 | 2.000 | EACH | | $600.00 |
| PEMBER COMPANIES, INC. | $242.33000 | 2.000 | EACH | | $484.66 |
| 0600 | 611.0615 | | INLET COVERS TYPE F | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $725.00000 | 6.000 | EACH | | $4,350.00 |
| MCCABE CONSTRUCTION, INC. | $696.00000 | 6.000 | EACH | | $4,176.00 |
| HOFFMAN CONSTRUCTION COMPANY | $700.00000 | 6.000 | EACH | | $4,200.00 |
| JAMES CAPE AND SONS COMPANY | $700.00000 | 6.000 | EACH | | $4,200.00 |
| PEMBER COMPANIES, INC. | $661.52000 | 6.000 | EACH | | $3,969.12 |
| 0610 | 611.0639 | | INLET COVERS TYPE H-S | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $390.00000 | 1.000 | EACH | | $390.00 |
| MCCABE CONSTRUCTION, INC. | $350.00000 | 1.000 | EACH | | $350.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 1.000 | EACH | | $400.00 |
| JAMES CAPE AND SONS COMPANY | $325.00000 | 1.000 | EACH | | $325.00 |
| PEMBER COMPANIES, INC. | $325.15000 | 1.000 | EACH | | $325.15 |
| 0620 | 611.0642 | | INLET COVERS TYPE MS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $260.00000 | 3.000 | EACH | | $780.00 |
| MCCABE CONSTRUCTION, INC. | $258.00000 | 3.000 | EACH | | $774.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 3.000 | EACH | | $1,200.00 |
| JAMES CAPE AND SONS COMPANY | $250.00000 | 3.000 | EACH | | $750.00 |
| PEMBER COMPANIES, INC. | $245.85000 | 3.000 | EACH | | $737.55 |
| 0630 | 611.0654 | | INLET COVERS TYPE V | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $380.00000 | 2.000 | EACH | | $760.00 |
| MCCABE CONSTRUCTION, INC. | $360.00000 | 2.000 | EACH | | $720.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 2.000 | EACH | | $800.00 |
| JAMES CAPE AND SONS COMPANY | $400.00000 | 2.000 | EACH | | $800.00 |
| PEMBER COMPANIES, INC. | $345.42000 | 2.000 | EACH | | $690.84 |
| 0640 | 611.8110 | | ADJUSTING MANHOLE COVERS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $240.00000 | 4.000 | EACH | | $960.00 |
| MCCABE CONSTRUCTION, INC. | $190.00000 | 4.000 | EACH | | $760.00 |
| HOFFMAN CONSTRUCTION COMPANY | $400.00000 | 4.000 | EACH | | $1,600.00 |
| JAMES CAPE AND SONS COMPANY | $75.00000 | 4.000 | EACH | | $300.00 |
| PEMBER COMPANIES, INC. | $215.56000 | 4.000 | EACH | | $862.24 |
| 0650 | 611.9710 | | SALVAGED INLET COVERS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $150.00000 | 1.000 | EACH | | $150.00 |
| MCCABE CONSTRUCTION, INC. | $100.00000 | 1.000 | EACH | | $100.00 |
| HOFFMAN CONSTRUCTION COMPANY | $300.00000 | 1.000 | EACH | | $300.00 |
| JAMES CAPE AND SONS COMPANY | $50.00000 | 1.000 | EACH | | $50.00 |
| PEMBER COMPANIES, INC. | $191.99000 | 1.000 | EACH | | $191.99 |
| 0660 | 614.0620.S | | MARKER POSTS CULVERT END FLEXIBLE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $32.00000 | 9.000 | EACH | | $288.00 |
| MCCABE CONSTRUCTION, INC. | $32.00000 | 9.000 | EACH | | $288.00 |
| HOFFMAN CONSTRUCTION COMPANY | $32.00000 | 9.000 | EACH | | $288.00 |
| JAMES CAPE AND SONS COMPANY | $32.00000 | 9.000 | EACH | | $288.00 |
| PEMBER COMPANIES, INC. | $36.77000 | 9.000 | EACH | | $330.93 |
| 0670 | 618.0100 | | MAINTENANCE AND REPAIR OF HAUL ROADS (PROJECT) 02. 8610-01-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,000.00000 | 1.000 | EACH | | $1,000.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 1.000 | EACH | | $1.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 1.000 | EACH | | $1.00 |
| JAMES CAPE AND SONS COMPANY | $1,000.00000 | 1.000 | EACH | | $1,000.00 |
| PEMBER COMPANIES, INC. | $2,163.46000 | 1.000 | EACH | | $2,163.46 |
| 0680 | 619.1000 | | MOBILIZATION | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $74,000.00000 | 1.000 | EACH | | $74,000.00 |
| MCCABE CONSTRUCTION, INC. | $86,000.00000 | 1.000 | EACH | | $86,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $72,000.00000 | 1.000 | EACH | | $72,000.00 |
| JAMES CAPE AND SONS COMPANY | $108,432.00000 | 1.000 | EACH | | $108,432.00 |
| PEMBER COMPANIES, INC. | $126,219.10000 | 1.000 | EACH | | $126,219.10 |
| 0690 | 620.0300 | | CONCRETE MEDIAN SLOPED NOSE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $5.00000 | 71.500 | SF | | $357.50 |
| MCCABE CONSTRUCTION, INC. | $5.00000 | 71.500 | SF | | $357.50 |
| HOFFMAN CONSTRUCTION COMPANY | $4.28000 | 71.500 | SF | | $306.02 |
| JAMES CAPE AND SONS COMPANY | $5.49000 | 71.500 | SF | | $392.54 |
| PEMBER COMPANIES, INC. | $5.68000 | 71.500 | SF | | $406.12 |
| 0700 | 624.0100 | | WATER | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $118.00000 | 4.000 | MGAL | | $472.00 |
| MCCABE CONSTRUCTION, INC. | $50.00000 | 4.000 | MGAL | | $200.00 |
| HOFFMAN CONSTRUCTION COMPANY | $22.00000 | 4.000 | MGAL | | $88.00 |
| JAMES CAPE AND SONS COMPANY | $50.00000 | 4.000 | MGAL | | $200.00 |
| PEMBER COMPANIES, INC. | $146.93000 | 4.000 | MGAL | | $587.72 |
| 0710 | 625.0100 | | TOPSOIL | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.68000 | 15,070.000 | SY | | $25,317.60 |
| MCCABE CONSTRUCTION, INC. | $2.25000 | 15,070.000 | SY | | $33,907.50 |
| HOFFMAN CONSTRUCTION COMPANY | $1.20000 | 15,070.000 | SY | | $18,084.00 |
| JAMES CAPE AND SONS COMPANY | $1.60000 | 15,070.000 | SY | | $24,112.00 |
| PEMBER COMPANIES, INC. | $0.66000 | 15,070.000 | SY | | $9,946.20 |
| 0720 | 625.0105 | | TOPSOIL | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $18.00000 | 60.000 | CY | | $1,080.00 |
| MCCABE CONSTRUCTION, INC. | $14.00000 | 60.000 | CY | | $840.00 |
| HOFFMAN CONSTRUCTION COMPANY | $16.00000 | 60.000 | CY | | $960.00 |
| JAMES CAPE AND SONS COMPANY | $12.00000 | 60.000 | CY | | $720.00 |
| PEMBER COMPANIES, INC. | $23.66000 | 60.000 | CY | | $1,419.60 |
| 0730 | 625.0500 | | SALVAGED TOPSOIL | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.00000 | 1,330.000 | SY | | $2,660.00 |
| MCCABE CONSTRUCTION, INC. | $1.70000 | 1,330.000 | SY | | $2,261.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.20000 | 1,330.000 | SY | | $1,596.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 1,330.000 | SY | | $1,330.00 |
| PEMBER COMPANIES, INC. | $0.79000 | 1,330.000 | SY | | $1,050.70 |
| 0740 | 627.0200 | | MULCHING | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.10000 | 16,551.000 | SY | | $1,655.10 |
| MCCABE CONSTRUCTION, INC. | $0.10000 | 16,551.000 | SY | | $1,655.10 |
| HOFFMAN CONSTRUCTION COMPANY | $0.10000 | 16,551.000 | SY | | $1,655.10 |
| JAMES CAPE AND SONS COMPANY | $0.10000 | 16,551.000 | SY | | $1,655.10 |
| PEMBER COMPANIES, INC. | $0.10000 | 16,551.000 | SY | | $1,655.10 |
| 0750 | 628.1105 | | EROSION BALES DELIVERED | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $7.00000 | 70.000 | EACH | | $490.00 |
| MCCABE CONSTRUCTION, INC. | $7.00000 | 70.000 | EACH | | $490.00 |
| HOFFMAN CONSTRUCTION COMPANY | $7.00000 | 70.000 | EACH | | $490.00 |
| JAMES CAPE AND SONS COMPANY | $7.00000 | 70.000 | EACH | | $490.00 |
| PEMBER COMPANIES, INC. | $3.41000 | 70.000 | EACH | | $238.70 |
| 0760 | 628.1110 | | EROSION BALES INSTALLED | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.00000 | 70.000 | EACH | | $140.00 |
| MCCABE CONSTRUCTION, INC. | $2.00000 | 70.000 | EACH | | $140.00 |
| HOFFMAN CONSTRUCTION COMPANY | $2.00000 | 70.000 | EACH | | $140.00 |
| JAMES CAPE AND SONS COMPANY | $2.00000 | 70.000 | EACH | | $140.00 |
| PEMBER COMPANIES, INC. | $5.67000 | 70.000 | EACH | | $396.90 |
| 0770 | 628.1505 | | SILT FENCE DELIVERED | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.75000 | 1,650.000 | LF | | $1,237.50 |
| MCCABE CONSTRUCTION, INC. | $0.75000 | 1,650.000 | LF | | $1,237.50 |
| HOFFMAN CONSTRUCTION COMPANY | $1.20000 | 1,650.000 | LF | | $1,980.00 |
| JAMES CAPE AND SONS COMPANY | $0.75000 | 1,650.000 | LF | | $1,237.50 |
| PEMBER COMPANIES, INC. | $0.62000 | 1,650.000 | LF | | $1,023.00 |
| 0780 | 628.1510 | | SILT FENCE INSTALLED | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.75000 | 1,650.000 | LF | | $1,237.50 |
| MCCABE CONSTRUCTION, INC. | $0.75000 | 1,650.000 | LF | | $1,237.50 |
| HOFFMAN CONSTRUCTION COMPANY | $1.20000 | 1,650.000 | LF | | $1,980.00 |
| JAMES CAPE AND SONS COMPANY | $0.75000 | 1,650.000 | LF | | $1,237.50 |
| PEMBER COMPANIES, INC. | $1.17000 | 1,650.000 | LF | | $1,930.50 |
| 0790 | 628.1520 | | SILT FENCE MAINTENANCE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.01000 | 1,800.000 | LF | | $18.00 |
| MCCABE CONSTRUCTION, INC. | $0.01000 | 1,800.000 | LF | | $18.00 |
| HOFFMAN CONSTRUCTION COMPANY | $0.20000 | 1,800.000 | LF | | $360.00 |
| JAMES CAPE AND SONS COMPANY | $0.01000 | 1,800.000 | LF | | $18.00 |
| PEMBER COMPANIES, INC. | $0.24000 | 1,800.000 | LF | | $432.00 |
| 0800 | 628.1905 | | MOBILIZATIONS EROSION CONTROL | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $250.00000 | 2.000 | EACH | | $500.00 |
| MCCABE CONSTRUCTION, INC. | $250.00000 | 2.000 | EACH | | $500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $250.00000 | 2.000 | EACH | | $500.00 |
| JAMES CAPE AND SONS COMPANY | $250.00000 | 2.000 | EACH | | $500.00 |
| PEMBER COMPANIES, INC. | $116.62000 | 2.000 | EACH | | $233.24 |
| 0810 | 628.1910 | | MOBILIZATIONS EMERGENCY EROSION CONTROL | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $25.00000 | 2.000 | EACH | | $50.00 |
| MCCABE CONSTRUCTION, INC. | $25.00000 | 2.000 | EACH | | $50.00 |
| HOFFMAN CONSTRUCTION COMPANY | $250.00000 | 2.000 | EACH | | $500.00 |
| JAMES CAPE AND SONS COMPANY | $25.00000 | 2.000 | EACH | | $50.00 |
| PEMBER COMPANIES, INC. | $116.62000 | 2.000 | EACH | | $233.24 |
| 0820 | 628.2015 | | EROSION MAT DELIVERED URBAN CLASS I TYPE A | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.25000 | 90.000 | SY | | $112.50 |
| MCCABE CONSTRUCTION, INC. | $1.25000 | 90.000 | SY | | $112.50 |
| HOFFMAN CONSTRUCTION COMPANY | $1.25000 | 90.000 | SY | | $112.50 |
| JAMES CAPE AND SONS COMPANY | $1.25000 | 90.000 | SY | | $112.50 |
| PEMBER COMPANIES, INC. | $1.41000 | 90.000 | SY | | $126.90 |
| 0830 | 628.3015 | | EROSION MAT INSTALLED URBAN CLASS I TYPE A | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.25000 | 90.000 | SY | | $112.50 |
| MCCABE CONSTRUCTION, INC. | $1.25000 | 90.000 | SY | | $112.50 |
| HOFFMAN CONSTRUCTION COMPANY | $1.25000 | 90.000 | SY | | $112.50 |
| JAMES CAPE AND SONS COMPANY | $1.25000 | 90.000 | SY | | $112.50 |
| PEMBER COMPANIES, INC. | $1.41000 | 90.000 | SY | | $126.90 |
| 0840 | 628.7005 | | INLET PROTECTION TYPE A | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $65.00000 | 17.000 | EACH | | $1,105.00 |
| MCCABE CONSTRUCTION, INC. | $65.00000 | 17.000 | EACH | | $1,105.00 |
| HOFFMAN CONSTRUCTION COMPANY | $65.00000 | 17.000 | EACH | | $1,105.00 |
| JAMES CAPE AND SONS COMPANY | $75.00000 | 17.000 | EACH | | $1,275.00 |
| PEMBER COMPANIES, INC. | $51.72000 | 17.000 | EACH | | $879.24 |
| 0850 | 628.7010 | | INLET PROTECTION TYPE B | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $35.00000 | 9.000 | EACH | | $315.00 |
| MCCABE CONSTRUCTION, INC. | $35.00000 | 9.000 | EACH | | $315.00 |
| HOFFMAN CONSTRUCTION COMPANY | $35.00000 | 9.000 | EACH | | $315.00 |
| JAMES CAPE AND SONS COMPANY | $20.00000 | 9.000 | EACH | | $180.00 |
| PEMBER COMPANIES, INC. | $33.10000 | 9.000 | EACH | | $297.90 |
| 0860 | 628.7015 | | INLET PROTECTION TYPE C | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $25.00000 | 8.000 | EACH | | $200.00 |
| MCCABE CONSTRUCTION, INC. | $25.00000 | 8.000 | EACH | | $200.00 |
| HOFFMAN CONSTRUCTION COMPANY | $25.00000 | 8.000 | EACH | | $200.00 |
| JAMES CAPE AND SONS COMPANY | $20.00000 | 8.000 | EACH | | $160.00 |
| PEMBER COMPANIES, INC. | $33.10000 | 8.000 | EACH | | $264.80 |
| 0870 | 629.0210 | | FERTILIZER TYPE B | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $30.00000 | 10.400 | CWT | | $312.00 |
| MCCABE CONSTRUCTION, INC. | $30.00000 | 10.400 | CWT | | $312.00 |
| HOFFMAN CONSTRUCTION COMPANY | $30.00000 | 10.400 | CWT | | $312.00 |
| JAMES CAPE AND SONS COMPANY | $30.00000 | 10.400 | CWT | | $312.00 |
| PEMBER COMPANIES, INC. | $34.30000 | 10.400 | CWT | | $356.72 |
| 0880 | 630.0140 | | SEEDING MIXTURE NO. 40 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $4.75000 | 299.000 | LB | | $1,420.25 |
| MCCABE CONSTRUCTION, INC. | $4.75000 | 299.000 | LB | | $1,420.25 |
| HOFFMAN CONSTRUCTION COMPANY | $4.75000 | 299.000 | LB | | $1,420.25 |
| JAMES CAPE AND SONS COMPANY | $4.75000 | 299.000 | LB | | $1,420.25 |
| PEMBER COMPANIES, INC. | $3.73000 | 299.000 | LB | | $1,115.27 |
| 0890 | 631.0300 | | SOD WATER | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $50.00000 | 1.000 | MGAL | | $50.00 |
| MCCABE CONSTRUCTION, INC. | $50.00000 | 1.000 | MGAL | | $50.00 |
| HOFFMAN CONSTRUCTION COMPANY | $50.00000 | 1.000 | MGAL | | $50.00 |
| JAMES CAPE AND SONS COMPANY | $50.00000 | 1.000 | MGAL | | $50.00 |
| PEMBER COMPANIES, INC. | $362.07000 | 1.000 | MGAL | | $362.07 |
| 0900 | 631.1000 | | SOD LAWN | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $4.00000 | 325.000 | SY | | $1,300.00 |
| MCCABE CONSTRUCTION, INC. | $4.00000 | 325.000 | SY | | $1,300.00 |
| HOFFMAN CONSTRUCTION COMPANY | $4.00000 | 325.000 | SY | | $1,300.00 |
| JAMES CAPE AND SONS COMPANY | $4.00000 | 325.000 | SY | | $1,300.00 |
| PEMBER COMPANIES, INC. | $3.32000 | 325.000 | SY | | $1,079.00 |
| 0910 | 634.0416 | | POSTS WOOD 4X4-INCH X 16-FT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $55.00000 | 34.000 | EACH | | $1,870.00 |
| MCCABE CONSTRUCTION, INC. | $38.00000 | 34.000 | EACH | | $1,292.00 |
| HOFFMAN CONSTRUCTION COMPANY | $38.00000 | 34.000 | EACH | | $1,292.00 |
| JAMES CAPE AND SONS COMPANY | $338.00000 | 34.000 | EACH | | $11,492.00 |
| PEMBER COMPANIES, INC. | $52.01000 | 34.000 | EACH | | $1,768.34 |
| 0920 | 637.0202 | | SIGNS REFLECTIVE TYPE II | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $13.00000 | 623.489 | SF | | $8,105.36 |
| MCCABE CONSTRUCTION, INC. | $12.75000 | 623.489 | SF | | $7,949.48 |
| HOFFMAN CONSTRUCTION COMPANY | $12.75000 | 623.489 | SF | | $7,949.48 |
| JAMES CAPE AND SONS COMPANY | $12.75000 | 623.489 | SF | | $7,949.48 |
| PEMBER COMPANIES, INC. | $18.05000 | 623.489 | SF | | $11,253.98 |
| 0930 | 638.2102 | | MOVING SIGNS TYPE II | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $15.00000 | 12.000 | EACH | | $180.00 |
| MCCABE CONSTRUCTION, INC. | $30.00000 | 12.000 | EACH | | $360.00 |
| HOFFMAN CONSTRUCTION COMPANY | $30.00000 | 12.000 | EACH | | $360.00 |
| JAMES CAPE AND SONS COMPANY | $30.00000 | 12.000 | EACH | | $360.00 |
| PEMBER COMPANIES, INC. | $70.14000 | 12.000 | EACH | | $841.68 |
| 0940 | 638.2602 | | REMOVING SIGNS TYPE II | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $13.00000 | 74.000 | EACH | | $962.00 |
| MCCABE CONSTRUCTION, INC. | $15.00000 | 74.000 | EACH | | $1,110.00 |
| HOFFMAN CONSTRUCTION COMPANY | $15.00000 | 74.000 | EACH | | $1,110.00 |
| JAMES CAPE AND SONS COMPANY | $15.00000 | 74.000 | EACH | | $1,110.00 |
| PEMBER COMPANIES, INC. | $20.05000 | 74.000 | EACH | | $1,483.70 |
| 0950 | 638.3000 | | REMOVING SMALL SIGN SUPPORTS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $13.00000 | 42.000 | EACH | | $546.00 |
| MCCABE CONSTRUCTION, INC. | $15.00000 | 42.000 | EACH | | $630.00 |
| HOFFMAN CONSTRUCTION COMPANY | $15.00000 | 42.000 | EACH | | $630.00 |
| JAMES CAPE AND SONS COMPANY | $15.00000 | 42.000 | EACH | | $630.00 |
| PEMBER COMPANIES, INC. | $20.05000 | 42.000 | EACH | | $842.10 |
| 0960 | 638.4000 | | MOVING SMALL SIGN SUPPORTS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $15.00000 | 9.000 | EACH | | $135.00 |
| MCCABE CONSTRUCTION, INC. | $50.00000 | 9.000 | EACH | | $450.00 |
| HOFFMAN CONSTRUCTION COMPANY | $50.00000 | 9.000 | EACH | | $450.00 |
| JAMES CAPE AND SONS COMPANY | $50.00000 | 9.000 | EACH | | $450.00 |
| PEMBER COMPANIES, INC. | $70.14000 | 9.000 | EACH | | $631.26 |
| 0970 | 641.1200 | | SIGN BRIDGE CANTILEVERED (STRUCTURE) 01. S-9-24 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3,500.00000 | 1.000 | LS | | $3,500.00 |
| MCCABE CONSTRUCTION, INC. | $3,500.00000 | 1.000 | LS | | $3,500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3,500.00000 | 1.000 | LS | | $3,500.00 |
| JAMES CAPE AND SONS COMPANY | $3,500.00000 | 1.000 | LS | | $3,500.00 |
| PEMBER COMPANIES, INC. | $5,950.50000 | 1.000 | LS | | $5,950.50 |
| 0980 | 641.6600 | | SIGN BRIDGE (STRUCTURE) 01. S-9-25 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $13,500.00000 | 1.000 | LS | | $13,500.00 |
| MCCABE CONSTRUCTION, INC. | $13,500.00000 | 1.000 | LS | | $13,500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $13,500.00000 | 1.000 | LS | | $13,500.00 |
| JAMES CAPE AND SONS COMPANY | $13,500.00000 | 1.000 | LS | | $13,500.00 |
| PEMBER COMPANIES, INC. | $17,747.36000 | 1.000 | LS | | $17,747.36 |
| 0990 | 642.5000 | | FIELD OFFICE TYPE B (PROJECT) | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3,900.00000 | 1.000 | EACH | | $3,900.00 |
| MCCABE CONSTRUCTION, INC. | $3,500.00000 | 1.000 | EACH | | $3,500.00 |
| HOFFMAN CONSTRUCTION COMPANY | $4,000.00000 | 1.000 | EACH | | $4,000.00 |
| JAMES CAPE AND SONS COMPANY | $5,000.00000 | 1.000 | EACH | | $5,000.00 |
| PEMBER COMPANIES, INC. | $2,971.86000 | 1.000 | EACH | | $2,971.86 |
| 1000 | 643.0200 | | TRAFFIC CONTROL SURVEILLANCE AND MAINTENANCE (PROJECT) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $35.00000 | 70.000 | DAYS | | $2,450.00 |
| MCCABE CONSTRUCTION, INC. | $35.00000 | 70.000 | DAYS | | $2,450.00 |
| HOFFMAN CONSTRUCTION COMPANY | $35.00000 | 70.000 | DAYS | | $2,450.00 |
| JAMES CAPE AND SONS COMPANY | $35.00000 | 70.000 | DAYS | | $2,450.00 |
| PEMBER COMPANIES, INC. | $36.21000 | 70.000 | DAYS | | $2,534.70 |
| 1010 | 643.0200 | | TRAFFIC CONTROL SURVEILLANCE AND MAINTENANCE (PROJECT) 02. 8610-01-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $35.00000 | 62.000 | DAYS | | $2,170.00 |
| MCCABE CONSTRUCTION, INC. | $35.00000 | 62.000 | DAYS | | $2,170.00 |
| HOFFMAN CONSTRUCTION COMPANY | $35.00000 | 62.000 | DAYS | | $2,170.00 |
| JAMES CAPE AND SONS COMPANY | $35.00000 | 62.000 | DAYS | | $2,170.00 |
| PEMBER COMPANIES, INC. | $36.21000 | 62.000 | DAYS | | $2,245.02 |
| 1020 | 643.0300 | | TRAFFIC CONTROL DRUMS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.20000 | 20,424.000 | DAYS | | $4,084.80 |
| MCCABE CONSTRUCTION, INC. | $0.20000 | 20,424.000 | DAYS | | $4,084.80 |
| HOFFMAN CONSTRUCTION COMPANY | $0.20000 | 20,424.000 | DAYS | | $4,084.80 |
| JAMES CAPE AND SONS COMPANY | $0.20000 | 20,424.000 | DAYS | | $4,084.80 |
| PEMBER COMPANIES, INC. | $0.21000 | 20,424.000 | DAYS | | $4,289.04 |
| 1030 | 643.0420 | | TRAFFIC CONTROL BARRICADES TYPE III | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.30000 | 3,570.000 | DAYS | | $1,071.00 |
| MCCABE CONSTRUCTION, INC. | $0.30000 | 3,570.000 | DAYS | | $1,071.00 |
| HOFFMAN CONSTRUCTION COMPANY | $0.30000 | 3,570.000 | DAYS | | $1,071.00 |
| JAMES CAPE AND SONS COMPANY | $0.30000 | 3,570.000 | DAYS | | $1,071.00 |
| PEMBER COMPANIES, INC. | $0.31000 | 3,570.000 | DAYS | | $1,106.70 |
| 1040 | 643.0500 | | TRAFFIC CONTROL FLEXIBLE TUBULAR MARKER POSTS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $20.00000 | 64.000 | EACH | | $1,280.00 |
| MCCABE CONSTRUCTION, INC. | $20.00000 | 64.000 | EACH | | $1,280.00 |
| HOFFMAN CONSTRUCTION COMPANY | $20.00000 | 64.000 | EACH | | $1,280.00 |
| JAMES CAPE AND SONS COMPANY | $20.00000 | 64.000 | EACH | | $1,280.00 |
| PEMBER COMPANIES, INC. | $20.69000 | 64.000 | EACH | | $1,324.16 |
| 1050 | 643.0600 | | TRAFFIC CONTROL FLEXIBLE TUBULAR MARKER BASES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.00000 | 64.000 | EACH | | $192.00 |
| MCCABE CONSTRUCTION, INC. | $3.00000 | 64.000 | EACH | | $192.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.00000 | 64.000 | EACH | | $192.00 |
| JAMES CAPE AND SONS COMPANY | $3.00000 | 64.000 | EACH | | $192.00 |
| PEMBER COMPANIES, INC. | $3.10000 | 64.000 | EACH | | $198.40 |
| 1060 | 643.0705 | | TRAFFIC CONTROL WARNING LIGHTS TYPE A | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.30000 | 6,356.000 | DAYS | | $1,906.80 |
| MCCABE CONSTRUCTION, INC. | $0.30000 | 6,356.000 | DAYS | | $1,906.80 |
| HOFFMAN CONSTRUCTION COMPANY | $0.30000 | 6,356.000 | DAYS | | $1,906.80 |
| JAMES CAPE AND SONS COMPANY | $0.30000 | 6,356.000 | DAYS | | $1,906.80 |
| PEMBER COMPANIES, INC. | $0.31000 | 6,356.000 | DAYS | | $1,970.36 |
| 1070 | 643.0715 | | TRAFFIC CONTROL WARNING LIGHTS TYPE C | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.40000 | 4,255.000 | DAYS | | $1,702.00 |
| MCCABE CONSTRUCTION, INC. | $0.40000 | 4,255.000 | DAYS | | $1,702.00 |
| HOFFMAN CONSTRUCTION COMPANY | $0.40000 | 4,255.000 | DAYS | | $1,702.00 |
| JAMES CAPE AND SONS COMPANY | $0.40000 | 4,255.000 | DAYS | | $1,702.00 |
| PEMBER COMPANIES, INC. | $0.41000 | 4,255.000 | DAYS | | $1,744.55 |
| 1080 | 643.0800 | | TRAFFIC CONTROL ARROW BOARDS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $20.00000 | 162.000 | DAYS | | $3,240.00 |
| MCCABE CONSTRUCTION, INC. | $20.00000 | 162.000 | DAYS | | $3,240.00 |
| HOFFMAN CONSTRUCTION COMPANY | $20.00000 | 162.000 | DAYS | | $3,240.00 |
| JAMES CAPE AND SONS COMPANY | $20.00000 | 162.000 | DAYS | | $3,240.00 |
| PEMBER COMPANIES, INC. | $20.69000 | 162.000 | DAYS | | $3,351.78 |
| 1090 | 643.0900 | | TRAFFIC CONTROL SIGNS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.40000 | 4,808.000 | DAYS | | $1,923.20 |
| MCCABE CONSTRUCTION, INC. | $0.40000 | 4,808.000 | DAYS | | $1,923.20 |
| HOFFMAN CONSTRUCTION COMPANY | $0.40000 | 4,808.000 | DAYS | | $1,923.20 |
| JAMES CAPE AND SONS COMPANY | $0.40000 | 4,808.000 | DAYS | | $1,923.20 |
| PEMBER COMPANIES, INC. | $0.41000 | 4,808.000 | DAYS | | $1,971.28 |
| 1100 | 643.0905.S | | TRAFFIC CONTROL COVERING SIGNS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $30.00000 | 16.000 | EACH | | $480.00 |
| MCCABE CONSTRUCTION, INC. | $30.00000 | 16.000 | EACH | | $480.00 |
| HOFFMAN CONSTRUCTION COMPANY | $30.00000 | 16.000 | EACH | | $480.00 |
| JAMES CAPE AND SONS COMPANY | $30.00000 | 16.000 | EACH | | $480.00 |
| PEMBER COMPANIES, INC. | $31.04000 | 16.000 | EACH | | $496.64 |
| 1110 | 643.3000 | | TRAFFIC CONTROL DETOUR SIGNS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.50000 | 5,656.000 | DAYS | | $2,828.00 |
| MCCABE CONSTRUCTION, INC. | $0.50000 | 5,656.000 | DAYS | | $2,828.00 |
| HOFFMAN CONSTRUCTION COMPANY | $0.50000 | 5,656.000 | DAYS | | $2,828.00 |
| JAMES CAPE AND SONS COMPANY | $0.50000 | 5,656.000 | DAYS | | $2,828.00 |
| PEMBER COMPANIES, INC. | $0.52000 | 5,656.000 | DAYS | | $2,941.12 |
| 1120 | 645.0110 | | GEOTEXTILE FABRIC TYPE DF | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.00000 | 216.000 | SY | | $432.00 |
| MCCABE CONSTRUCTION, INC. | $2.00000 | 216.000 | SY | | $432.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.30000 | 216.000 | SY | | $712.80 |
| JAMES CAPE AND SONS COMPANY | $4.00000 | 216.000 | SY | | $864.00 |
| PEMBER COMPANIES, INC. | $4.11000 | 216.000 | SY | | $887.76 |
| 1130 | 646.0106 | | PAVEMENT MARKING EPOXY 4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.32000 | 13,696.000 | LF | | $4,382.72 |
| MCCABE CONSTRUCTION, INC. | $0.54000 | 13,696.000 | LF | | $7,395.84 |
| HOFFMAN CONSTRUCTION COMPANY | $0.54000 | 13,696.000 | LF | | $7,395.84 |
| JAMES CAPE AND SONS COMPANY | $0.32000 | 13,696.000 | LF | | $4,382.72 |
| PEMBER COMPANIES, INC. | $0.33000 | 13,696.000 | LF | | $4,519.68 |
| 1140 | 646.0226 | | PAVEMENT MARKING CHANNELIZING EPOXY 8-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.60000 | 3,955.000 | LF | | $2,373.00 |
| MCCABE CONSTRUCTION, INC. | $0.60000 | 3,955.000 | LF | | $2,373.00 |
| HOFFMAN CONSTRUCTION COMPANY | $0.60000 | 3,955.000 | LF | | $2,373.00 |
| JAMES CAPE AND SONS COMPANY | $0.60000 | 3,955.000 | LF | | $2,373.00 |
| PEMBER COMPANIES, INC. | $0.62000 | 3,955.000 | LF | | $2,452.10 |
| 1150 | 646.0600 | | REMOVING PAVEMENT MARKINGS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.24000 | 9,262.000 | LF | | $2,222.88 |
| MCCABE CONSTRUCTION, INC. | $0.24000 | 9,262.000 | LF | | $2,222.88 |
| HOFFMAN CONSTRUCTION COMPANY | $0.24000 | 9,262.000 | LF | | $2,222.88 |
| JAMES CAPE AND SONS COMPANY | $0.24000 | 9,262.000 | LF | | $2,222.88 |
| PEMBER COMPANIES, INC. | $0.25000 | 9,262.000 | LF | | $2,315.50 |
| 1160 | 647.0156 | | PAVEMENT MARKING ARROWS EPOXY TYPE 1 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $100.00000 | 7.000 | EACH | | $700.00 |
| MCCABE CONSTRUCTION, INC. | $125.00000 | 7.000 | EACH | | $875.00 |
| HOFFMAN CONSTRUCTION COMPANY | $125.00000 | 7.000 | EACH | | $875.00 |
| JAMES CAPE AND SONS COMPANY | $100.00000 | 7.000 | EACH | | $700.00 |
| PEMBER COMPANIES, INC. | $103.45000 | 7.000 | EACH | | $724.15 |
| 1170 | 647.0166 | | PAVEMENT MARKING ARROWS EPOXY TYPE 2 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $100.00000 | 10.000 | EACH | | $1,000.00 |
| MCCABE CONSTRUCTION, INC. | $125.00000 | 10.000 | EACH | | $1,250.00 |
| HOFFMAN CONSTRUCTION COMPANY | $125.00000 | 10.000 | EACH | | $1,250.00 |
| JAMES CAPE AND SONS COMPANY | $100.00000 | 10.000 | EACH | | $1,000.00 |
| PEMBER COMPANIES, INC. | $103.45000 | 10.000 | EACH | | $1,034.50 |
| 1180 | 647.0356 | | PAVEMENT MARKING WORDS EPOXY | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $100.00000 | 14.000 | EACH | | $1,400.00 |
| MCCABE CONSTRUCTION, INC. | $125.00000 | 14.000 | EACH | | $1,750.00 |
| HOFFMAN CONSTRUCTION COMPANY | $125.00000 | 14.000 | EACH | | $1,750.00 |
| JAMES CAPE AND SONS COMPANY | $100.00000 | 14.000 | EACH | | $1,400.00 |
| PEMBER COMPANIES, INC. | $103.45000 | 14.000 | EACH | | $1,448.30 |
| 1190 | 647.0456 | | PAVEMENT MARKING CURB EPOXY | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.00000 | 520.000 | LF | | $1,560.00 |
| MCCABE CONSTRUCTION, INC. | $3.30000 | 520.000 | LF | | $1,716.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.30000 | 520.000 | LF | | $1,716.00 |
| JAMES CAPE AND SONS COMPANY | $3.00000 | 520.000 | LF | | $1,560.00 |
| PEMBER COMPANIES, INC. | $3.10000 | 520.000 | LF | | $1,612.00 |
| 1200 | 647.0506 | | PAVEMENT MARKING CURB RAMP EPOXY | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.00000 | 140.000 | LF | | $420.00 |
| MCCABE CONSTRUCTION, INC. | $3.30000 | 140.000 | LF | | $462.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.30000 | 140.000 | LF | | $462.00 |
| JAMES CAPE AND SONS COMPANY | $3.00000 | 140.000 | LF | | $420.00 |
| PEMBER COMPANIES, INC. | $3.10000 | 140.000 | LF | | $434.00 |
| 1210 | 647.0566 | | PAVEMENT MARKING STOP LINE EPOXY 18-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $4.00000 | 446.000 | LF | | $1,784.00 |
| MCCABE CONSTRUCTION, INC. | $3.40000 | 446.000 | LF | | $1,516.40 |
| HOFFMAN CONSTRUCTION COMPANY | $3.40000 | 446.000 | LF | | $1,516.40 |
| JAMES CAPE AND SONS COMPANY | $4.00000 | 446.000 | LF | | $1,784.00 |
| PEMBER COMPANIES, INC. | $4.14000 | 446.000 | LF | | $1,846.44 |
| 1220 | 647.0606 | | PAVEMENT MARKING ISLAND NOSE EPOXY | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $50.00000 | 5.000 | EACH | | $250.00 |
| MCCABE CONSTRUCTION, INC. | $45.00000 | 5.000 | EACH | | $225.00 |
| HOFFMAN CONSTRUCTION COMPANY | $45.00000 | 5.000 | EACH | | $225.00 |
| JAMES CAPE AND SONS COMPANY | $50.00000 | 5.000 | EACH | | $250.00 |
| PEMBER COMPANIES, INC. | $51.72000 | 5.000 | EACH | | $258.60 |
| 1230 | 647.0726 | | PAVEMENT MARKING DIAGONAL EPOXY 12-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.75000 | 51.000 | LF | | $191.25 |
| MCCABE CONSTRUCTION, INC. | $3.30000 | 51.000 | LF | | $168.30 |
| HOFFMAN CONSTRUCTION COMPANY | $3.30000 | 51.000 | LF | | $168.30 |
| JAMES CAPE AND SONS COMPANY | $3.75000 | 51.000 | LF | | $191.25 |
| PEMBER COMPANIES, INC. | $3.88000 | 51.000 | LF | | $197.88 |
| 1240 | 647.0766 | | PAVEMENT MARKING CROSSWALK EPOXY 6-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.25000 | 1,059.000 | LF | | $3,441.75 |
| MCCABE CONSTRUCTION, INC. | $3.30000 | 1,059.000 | LF | | $3,494.70 |
| HOFFMAN CONSTRUCTION COMPANY | $3.30000 | 1,059.000 | LF | | $3,494.70 |
| JAMES CAPE AND SONS COMPANY | $3.25000 | 1,059.000 | LF | | $3,441.75 |
| PEMBER COMPANIES, INC. | $3.36000 | 1,059.000 | LF | | $3,558.24 |
| 1250 | 647.0955 | | REMOVING PAVEMENT MARKINGS ARROWS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $30.00000 | 11.000 | EACH | | $330.00 |
| MCCABE CONSTRUCTION, INC. | $30.00000 | 11.000 | EACH | | $330.00 |
| HOFFMAN CONSTRUCTION COMPANY | $30.00000 | 11.000 | EACH | | $330.00 |
| JAMES CAPE AND SONS COMPANY | $30.00000 | 11.000 | EACH | | $330.00 |
| PEMBER COMPANIES, INC. | $31.03000 | 11.000 | EACH | | $341.33 |
| 1260 | 649.0100 | | TEMPORARY PAVEMENT MARKING 4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.20000 | 5,600.000 | LF | | $1,120.00 |
| MCCABE CONSTRUCTION, INC. | $0.20000 | 5,600.000 | LF | | $1,120.00 |
| HOFFMAN CONSTRUCTION COMPANY | $0.20000 | 5,600.000 | LF | | $1,120.00 |
| JAMES CAPE AND SONS COMPANY | $0.20000 | 5,600.000 | LF | | $1,120.00 |
| PEMBER COMPANIES, INC. | $0.21000 | 5,600.000 | LF | | $1,176.00 |
| 1270 | 649.0200 | | TEMPORARY PAVEMENT MARKING REFLECTIVE PAINT 4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.20000 | 14,933.000 | LF | | $2,986.60 |
| MCCABE CONSTRUCTION, INC. | $0.20000 | 14,933.000 | LF | | $2,986.60 |
| HOFFMAN CONSTRUCTION COMPANY | $0.20000 | 14,933.000 | LF | | $2,986.60 |
| JAMES CAPE AND SONS COMPANY | $0.20000 | 14,933.000 | LF | | $2,986.60 |
| PEMBER COMPANIES, INC. | $0.21000 | 14,933.000 | LF | | $3,135.93 |
| 1280 | 649.0400 | | TEMPORARY PAVEMENT MARKING REMOVABLE TAPE 4-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.80000 | 18,342.000 | LF | | $14,673.60 |
| MCCABE CONSTRUCTION, INC. | $0.80000 | 18,342.000 | LF | | $14,673.60 |
| HOFFMAN CONSTRUCTION COMPANY | $0.80000 | 18,342.000 | LF | | $14,673.60 |
| JAMES CAPE AND SONS COMPANY | $0.80000 | 18,342.000 | LF | | $14,673.60 |
| PEMBER COMPANIES, INC. | $0.83000 | 18,342.000 | LF | | $15,223.86 |
| 1290 | 649.0800 | | TEMPORARY PAVEMENT MARKING CHANNELIZING REMOVABLE TAPE 8-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.60000 | 1,825.000 | LF | | $2,920.00 |
| MCCABE CONSTRUCTION, INC. | $1.60000 | 1,825.000 | LF | | $2,920.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.60000 | 1,825.000 | LF | | $2,920.00 |
| JAMES CAPE AND SONS COMPANY | $1.60000 | 1,825.000 | LF | | $2,920.00 |
| PEMBER COMPANIES, INC. | $1.66000 | 1,825.000 | LF | | $3,029.50 |
| 1300 | 649.1000 | | TEMPORARY PAVEMENT MARKING STOP LINE REMOVABLE TAPE 12-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.40000 | 322.000 | LF | | $772.80 |
| MCCABE CONSTRUCTION, INC. | $2.40000 | 322.000 | LF | | $772.80 |
| HOFFMAN CONSTRUCTION COMPANY | $2.40000 | 322.000 | LF | | $772.80 |
| JAMES CAPE AND SONS COMPANY | $2.40000 | 322.000 | LF | | $772.80 |
| PEMBER COMPANIES, INC. | $2.48000 | 322.000 | LF | | $798.56 |
| 1310 | 649.1700 | | TEMPORARY PAVEMENT MARKING ARROWS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $30.00000 | 11.000 | EACH | | $330.00 |
| MCCABE CONSTRUCTION, INC. | $30.00000 | 11.000 | EACH | | $330.00 |
| HOFFMAN CONSTRUCTION COMPANY | $30.00000 | 11.000 | EACH | | $330.00 |
| JAMES CAPE AND SONS COMPANY | $30.00000 | 11.000 | EACH | | $330.00 |
| PEMBER COMPANIES, INC. | $31.03000 | 11.000 | EACH | | $341.33 |
| 1320 | 650.4000 | | CONSTRUCTION STAKING STORM SEWER SYSTEM | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $125.00000 | 2.000 | EACH | | $250.00 |
| MCCABE CONSTRUCTION, INC. | $125.00000 | 2.000 | EACH | | $250.00 |
| HOFFMAN CONSTRUCTION COMPANY | $125.00000 | 2.000 | EACH | | $250.00 |
| JAMES CAPE AND SONS COMPANY | $125.00000 | 2.000 | EACH | | $250.00 |
| PEMBER COMPANIES, INC. | $129.31000 | 2.000 | EACH | | $258.62 |
| 1330 | 650.4500 | | CONSTRUCTION STAKING SUBGRADE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.45000 | 7,057.000 | LF | | $3,175.65 |
| MCCABE CONSTRUCTION, INC. | $0.45000 | 7,057.000 | LF | | $3,175.65 |
| HOFFMAN CONSTRUCTION COMPANY | $0.45000 | 7,057.000 | LF | | $3,175.65 |
| JAMES CAPE AND SONS COMPANY | $0.45000 | 7,057.000 | LF | | $3,175.65 |
| PEMBER COMPANIES, INC. | $0.47000 | 7,057.000 | LF | | $3,316.79 |
| 1340 | 650.5000 | | CONSTRUCTION STAKING BASE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.50000 | 2,435.000 | LF | | $1,217.50 |
| MCCABE CONSTRUCTION, INC. | $0.50000 | 2,435.000 | LF | | $1,217.50 |
| HOFFMAN CONSTRUCTION COMPANY | $0.50000 | 2,435.000 | LF | | $1,217.50 |
| JAMES CAPE AND SONS COMPANY | $0.50000 | 2,435.000 | LF | | $1,217.50 |
| PEMBER COMPANIES, INC. | $0.52000 | 2,435.000 | LF | | $1,266.20 |
| 1350 | 650.5500 | | CONSTRUCTION STAKING CURB GUTTER AND CURB & GUTTER | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.00000 | 750.000 | LF | | $750.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 750.000 | LF | | $750.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 750.000 | LF | | $750.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 750.000 | LF | | $750.00 |
| PEMBER COMPANIES, INC. | $1.03000 | 750.000 | LF | | $772.50 |
| 1360 | 650.7000 | | CONSTRUCTION STAKING CONCRETE PAVEMENT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.80000 | 2,822.000 | LF | | $2,257.60 |
| MCCABE CONSTRUCTION, INC. | $0.80000 | 2,822.000 | LF | | $2,257.60 |
| HOFFMAN CONSTRUCTION COMPANY | $0.80000 | 2,822.000 | LF | | $2,257.60 |
| JAMES CAPE AND SONS COMPANY | $0.80000 | 2,822.000 | LF | | $2,257.60 |
| PEMBER COMPANIES, INC. | $0.83000 | 2,822.000 | LF | | $2,342.26 |
| 1370 | 650.8500 | | CONSTRUCTION STAKING ELECTRICAL INSTALLATIONS (PROJECT) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,500.00000 | 1.000 | LS | | $1,500.00 |
| MCCABE CONSTRUCTION, INC. | $1,000.00000 | 1.000 | LS | | $1,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,000.00000 | 1.000 | LS | | $1,000.00 |
| JAMES CAPE AND SONS COMPANY | $1,000.00000 | 1.000 | LS | | $1,000.00 |
| PEMBER COMPANIES, INC. | $1,034.50000 | 1.000 | LS | | $1,034.50 |
| 1380 | 650.8500 | | CONSTRUCTION STAKING ELECTRICAL INSTALLATIONS (PROJECT) 02. 8610-01-01 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,500.00000 | 1.000 | LS | | $1,500.00 |
| MCCABE CONSTRUCTION, INC. | $1,000.00000 | 1.000 | LS | | $1,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,000.00000 | 1.000 | LS | | $1,000.00 |
| JAMES CAPE AND SONS COMPANY | $1,000.00000 | 1.000 | LS | | $1,000.00 |
| PEMBER COMPANIES, INC. | $1,034.50000 | 1.000 | LS | | $1,034.50 |
| 1390 | 650.9900 | | CONSTRUCTION STAKING INITIAL LAYOUT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.25000 | 8,906.000 | LF | | $11,132.50 |
| MCCABE CONSTRUCTION, INC. | $1.25000 | 8,906.000 | LF | | $11,132.50 |
| HOFFMAN CONSTRUCTION COMPANY | $1.25000 | 8,906.000 | LF | | $11,132.50 |
| JAMES CAPE AND SONS COMPANY | $1.25000 | 8,906.000 | LF | | $11,132.50 |
| PEMBER COMPANIES, INC. | $1.29000 | 8,906.000 | LF | | $11,488.74 |
| 1400 | 651.5000.S | | INSTALL EMERGENCY VEHICLE PREEMPTION (EVP) CONTROLLER WISDOT OWNED TRAFFIC SIGNALS (INTERSECTION) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $515.00000 | 1.000 | LS | | $515.00 |
| MCCABE CONSTRUCTION, INC. | $515.00000 | 1.000 | LS | | $515.00 |
| HOFFMAN CONSTRUCTION COMPANY | $515.00000 | 1.000 | LS | | $515.00 |
| JAMES CAPE AND SONS COMPANY | $515.00000 | 1.000 | LS | | $515.00 |
| PEMBER COMPANIES, INC. | $532.77000 | 1.000 | LS | | $532.77 |
| 1410 | 651.5000.S | | INSTALL EMERGENCY VEHICLE PREEMPTION (EVP) CONTROLLER WISDOT OWNED TRAFFIC SIGNALS (INTERSECTION) 02. 8610-01-01 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $515.00000 | 1.000 | LS | | $515.00 |
| MCCABE CONSTRUCTION, INC. | $515.00000 | 1.000 | LS | | $515.00 |
| HOFFMAN CONSTRUCTION COMPANY | $515.00000 | 1.000 | LS | | $515.00 |
| JAMES CAPE AND SONS COMPANY | $515.00000 | 1.000 | LS | | $515.00 |
| PEMBER COMPANIES, INC. | $532.77000 | 1.000 | LS | | $532.77 |
| 1420 | 652.0210 | | CONDUIT RIGID NONMETALLIC SCHEDULE 40 1-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.32000 | 36.000 | LF | | $119.52 |
| MCCABE CONSTRUCTION, INC. | $3.32000 | 36.000 | LF | | $119.52 |
| HOFFMAN CONSTRUCTION COMPANY | $3.32000 | 36.000 | LF | | $119.52 |
| JAMES CAPE AND SONS COMPANY | $3.32000 | 36.000 | LF | | $119.52 |
| PEMBER COMPANIES, INC. | $3.43000 | 36.000 | LF | | $123.48 |
| 1430 | 652.0225 | | CONDUIT RIGID NONMETALLIC SCHEDULE 40 2-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.22000 | 5,776.000 | LF | | $12,822.72 |
| MCCABE CONSTRUCTION, INC. | $2.22000 | 5,776.000 | LF | | $12,822.72 |
| HOFFMAN CONSTRUCTION COMPANY | $2.22000 | 5,776.000 | LF | | $12,822.72 |
| JAMES CAPE AND SONS COMPANY | $2.22000 | 5,776.000 | LF | | $12,822.72 |
| PEMBER COMPANIES, INC. | $2.30000 | 5,776.000 | LF | | $13,284.80 |
| 1440 | 652.0235 | | CONDUIT RIGID NONMETALLIC SCHEDULE 40 3-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3.24000 | 3,675.000 | LF | | $11,907.00 |
| MCCABE CONSTRUCTION, INC. | $3.24000 | 3,675.000 | LF | | $11,907.00 |
| HOFFMAN CONSTRUCTION COMPANY | $3.24000 | 3,675.000 | LF | | $11,907.00 |
| JAMES CAPE AND SONS COMPANY | $3.24000 | 3,675.000 | LF | | $11,907.00 |
| PEMBER COMPANIES, INC. | $3.35000 | 3,675.000 | LF | | $12,311.25 |
| 1450 | 652.0800 | | CONDUIT LOOP DETECTOR | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.33000 | 3,510.000 | LF | | $8,178.30 |
| MCCABE CONSTRUCTION, INC. | $2.33000 | 3,510.000 | LF | | $8,178.30 |
| HOFFMAN CONSTRUCTION COMPANY | $2.33000 | 3,510.000 | LF | | $8,178.30 |
| JAMES CAPE AND SONS COMPANY | $2.33000 | 3,510.000 | LF | | $8,178.30 |
| PEMBER COMPANIES, INC. | $2.41000 | 3,510.000 | LF | | $8,459.10 |
| 1460 | 653.0135 | | PULL BOXES STEEL 24X36-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $462.00000 | 30.000 | EACH | | $13,860.00 |
| MCCABE CONSTRUCTION, INC. | $462.00000 | 30.000 | EACH | | $13,860.00 |
| HOFFMAN CONSTRUCTION COMPANY | $462.00000 | 30.000 | EACH | | $13,860.00 |
| JAMES CAPE AND SONS COMPANY | $462.00000 | 30.000 | EACH | | $13,860.00 |
| PEMBER COMPANIES, INC. | $477.94000 | 30.000 | EACH | | $14,338.20 |
| 1470 | 653.0140 | | PULL BOXES STEEL 24X42-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $478.00000 | 29.000 | EACH | | $13,862.00 |
| MCCABE CONSTRUCTION, INC. | $478.00000 | 29.000 | EACH | | $13,862.00 |
| HOFFMAN CONSTRUCTION COMPANY | $478.00000 | 29.000 | EACH | | $13,862.00 |
| JAMES CAPE AND SONS COMPANY | $478.00000 | 29.000 | EACH | | $13,862.00 |
| PEMBER COMPANIES, INC. | $494.49000 | 29.000 | EACH | | $14,340.21 |
| 1480 | 654.0101 | | CONCRETE BASES TYPE 1 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $358.00000 | 19.000 | EACH | | $6,802.00 |
| MCCABE CONSTRUCTION, INC. | $358.00000 | 19.000 | EACH | | $6,802.00 |
| HOFFMAN CONSTRUCTION COMPANY | $358.00000 | 19.000 | EACH | | $6,802.00 |
| JAMES CAPE AND SONS COMPANY | $358.00000 | 19.000 | EACH | | $6,802.00 |
| PEMBER COMPANIES, INC. | $370.35000 | 19.000 | EACH | | $7,036.65 |
| 1490 | 654.0102 | | CONCRETE BASES TYPE 2 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $593.00000 | 9.000 | EACH | | $5,337.00 |
| MCCABE CONSTRUCTION, INC. | $593.00000 | 9.000 | EACH | | $5,337.00 |
| HOFFMAN CONSTRUCTION COMPANY | $593.00000 | 9.000 | EACH | | $5,337.00 |
| JAMES CAPE AND SONS COMPANY | $593.00000 | 9.000 | EACH | | $5,337.00 |
| PEMBER COMPANIES, INC. | $613.46000 | 9.000 | EACH | | $5,521.14 |
| 1500 | 654.0105 | | CONCRETE BASES TYPE 5 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $503.00000 | 16.000 | EACH | | $8,048.00 |
| MCCABE CONSTRUCTION, INC. | $503.00000 | 16.000 | EACH | | $8,048.00 |
| HOFFMAN CONSTRUCTION COMPANY | $503.00000 | 16.000 | EACH | | $8,048.00 |
| JAMES CAPE AND SONS COMPANY | $503.00000 | 16.000 | EACH | | $8,048.00 |
| PEMBER COMPANIES, INC. | $520.35000 | 16.000 | EACH | | $8,325.60 |
| 1510 | 654.0215 | | CONCRETE CONTROL CABINET BASES TYPE 9 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,134.00000 | 2.000 | EACH | | $2,268.00 |
| MCCABE CONSTRUCTION, INC. | $1,134.00000 | 2.000 | EACH | | $2,268.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,134.00000 | 2.000 | EACH | | $2,268.00 |
| JAMES CAPE AND SONS COMPANY | $1,134.00000 | 2.000 | EACH | | $2,268.00 |
| PEMBER COMPANIES, INC. | $1,173.12000 | 2.000 | EACH | | $2,346.24 |
| 1520 | 655.0210 | | CABLE TRAFFIC SIGNAL 3-14 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.00000 | 90.000 | LF | | $90.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 90.000 | LF | | $90.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 90.000 | LF | | $90.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 90.000 | LF | | $90.00 |
| PEMBER COMPANIES, INC. | $1.03000 | 90.000 | LF | | $92.70 |
| 1530 | 655.0230 | | CABLE TRAFFIC SIGNAL 5-14 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.64000 | 5,170.000 | LF | | $3,308.80 |
| MCCABE CONSTRUCTION, INC. | $0.64000 | 5,170.000 | LF | | $3,308.80 |
| HOFFMAN CONSTRUCTION COMPANY | $0.64000 | 5,170.000 | LF | | $3,308.80 |
| JAMES CAPE AND SONS COMPANY | $0.64000 | 5,170.000 | LF | | $3,308.80 |
| PEMBER COMPANIES, INC. | $0.66000 | 5,170.000 | LF | | $3,412.20 |
| 1540 | 655.0240 | | CABLE TRAFFIC SIGNAL 7-14 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.65000 | 1,978.000 | LF | | $1,285.70 |
| MCCABE CONSTRUCTION, INC. | $0.65000 | 1,978.000 | LF | | $1,285.70 |
| HOFFMAN CONSTRUCTION COMPANY | $0.65000 | 1,978.000 | LF | | $1,285.70 |
| JAMES CAPE AND SONS COMPANY | $0.65000 | 1,978.000 | LF | | $1,285.70 |
| PEMBER COMPANIES, INC. | $0.67000 | 1,978.000 | LF | | $1,325.26 |
| 1550 | 655.0260 | | CABLE TRAFFIC SIGNAL 12-14 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.00000 | 875.000 | LF | | $875.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 875.000 | LF | | $875.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 875.000 | LF | | $875.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 875.000 | LF | | $875.00 |
| PEMBER COMPANIES, INC. | $1.03000 | 875.000 | LF | | $901.25 |
| 1560 | 655.0315 | | CABLE TYPE UF 2-10 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.93000 | 3,547.000 | LF | | $3,298.71 |
| MCCABE CONSTRUCTION, INC. | $0.93000 | 3,547.000 | LF | | $3,298.71 |
| HOFFMAN CONSTRUCTION COMPANY | $0.93000 | 3,547.000 | LF | | $3,298.71 |
| JAMES CAPE AND SONS COMPANY | $0.93000 | 3,547.000 | LF | | $3,298.71 |
| PEMBER COMPANIES, INC. | $0.96000 | 3,547.000 | LF | | $3,405.12 |
| 1570 | 655.0515 | | ELECTRICAL WIRE TRAFFIC SIGNALS 10 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.41000 | 9,616.000 | LF | | $3,942.56 |
| MCCABE CONSTRUCTION, INC. | $0.41000 | 9,616.000 | LF | | $3,942.56 |
| HOFFMAN CONSTRUCTION COMPANY | $0.41000 | 9,616.000 | LF | | $3,942.56 |
| JAMES CAPE AND SONS COMPANY | $0.41000 | 9,616.000 | LF | | $3,942.56 |
| PEMBER COMPANIES, INC. | $0.42000 | 9,616.000 | LF | | $4,038.72 |
| 1580 | 655.0610 | | ELECTRICAL WIRE LIGHTING 12 AWG | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.40000 | 3,227.000 | LF | | $1,290.80 |
| MCCABE CONSTRUCTION, INC. | $0.40000 | 3,227.000 | LF | | $1,290.80 |
| HOFFMAN CONSTRUCTION COMPANY | $0.40000 | 3,227.000 | LF | | $1,290.80 |
| JAMES CAPE AND SONS COMPANY | $0.40000 | 3,227.000 | LF | | $1,290.80 |
| PEMBER COMPANIES, INC. | $0.41000 | 3,227.000 | LF | | $1,323.07 |
| 1590 | 655.0700 | | LOOP DETECTOR LEAD IN CABLE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.70000 | 12,324.000 | LF | | $8,626.80 |
| MCCABE CONSTRUCTION, INC. | $0.70000 | 12,324.000 | LF | | $8,626.80 |
| HOFFMAN CONSTRUCTION COMPANY | $0.70000 | 12,324.000 | LF | | $8,626.80 |
| JAMES CAPE AND SONS COMPANY | $0.70000 | 12,324.000 | LF | | $8,626.80 |
| PEMBER COMPANIES, INC. | $0.72000 | 12,324.000 | LF | | $8,873.28 |
| 1600 | 655.0800 | | LOOP DETECTOR WIRE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $0.37000 | 8,949.000 | LF | | $3,311.13 |
| MCCABE CONSTRUCTION, INC. | $0.37000 | 8,949.000 | LF | | $3,311.13 |
| HOFFMAN CONSTRUCTION COMPANY | $0.37000 | 8,949.000 | LF | | $3,311.13 |
| JAMES CAPE AND SONS COMPANY | $0.37000 | 8,949.000 | LF | | $3,311.13 |
| PEMBER COMPANIES, INC. | $0.38000 | 8,949.000 | LF | | $3,400.62 |
| 1610 | 656.0200 | | ELECTRICAL SERVICE METER BREAKER PEDESTAL (LOCATION) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $879.00000 | 1.000 | LS | | $879.00 |
| MCCABE CONSTRUCTION, INC. | $879.00000 | 1.000 | LS | | $879.00 |
| HOFFMAN CONSTRUCTION COMPANY | $879.00000 | 1.000 | LS | | $879.00 |
| JAMES CAPE AND SONS COMPANY | $879.00000 | 1.000 | LS | | $879.00 |
| PEMBER COMPANIES, INC. | $909.32000 | 1.000 | LS | | $909.32 |
| 1620 | 656.0200 | | ELECTRICAL SERVICE METER BREAKER PEDESTAL (LOCATION) 02. 8610-01-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $879.00000 | 1.000 | LS | | $879.00 |
| MCCABE CONSTRUCTION, INC. | $879.00000 | 1.000 | LS | | $879.00 |
| HOFFMAN CONSTRUCTION COMPANY | $879.00000 | 1.000 | LS | | $879.00 |
| JAMES CAPE AND SONS COMPANY | $879.00000 | 1.000 | LS | | $879.00 |
| PEMBER COMPANIES, INC. | $909.32000 | 1.000 | LS | | $909.32 |
| 1630 | 657.0100 | | PEDESTAL BASES | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $131.00000 | 19.000 | EACH | | $2,489.00 |
| MCCABE CONSTRUCTION, INC. | $131.00000 | 19.000 | EACH | | $2,489.00 |
| HOFFMAN CONSTRUCTION COMPANY | $131.00000 | 19.000 | EACH | | $2,489.00 |
| JAMES CAPE AND SONS COMPANY | $131.00000 | 19.000 | EACH | | $2,489.00 |
| PEMBER COMPANIES, INC. | $135.52000 | 19.000 | EACH | | $2,574.88 |
| 1640 | 657.0255 | | TRANSFORMER BASES STANDARD 11 1/2-INCH BOLT CIRCLE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $237.00000 | 24.000 | EACH | | $5,688.00 |
| MCCABE CONSTRUCTION, INC. | $237.00000 | 24.000 | EACH | | $5,688.00 |
| HOFFMAN CONSTRUCTION COMPANY | $237.00000 | 24.000 | EACH | | $5,688.00 |
| JAMES CAPE AND SONS COMPANY | $237.00000 | 24.000 | EACH | | $5,688.00 |
| PEMBER COMPANIES, INC. | $245.18000 | 24.000 | EACH | | $5,884.32 |
| 1650 | 657.0320 | | POLES TYPE 5 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $468.00000 | 16.000 | EACH | | $7,488.00 |
| MCCABE CONSTRUCTION, INC. | $468.00000 | 16.000 | EACH | | $7,488.00 |
| HOFFMAN CONSTRUCTION COMPANY | $468.00000 | 16.000 | EACH | | $7,488.00 |
| JAMES CAPE AND SONS COMPANY | $468.00000 | 16.000 | EACH | | $7,488.00 |
| PEMBER COMPANIES, INC. | $484.15000 | 16.000 | EACH | | $7,746.40 |
| 1660 | 657.0395.S | | POLES (TYPE) 01. 2 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $775.00000 | 9.000 | EACH | | $6,975.00 |
| MCCABE CONSTRUCTION, INC. | $775.00000 | 9.000 | EACH | | $6,975.00 |
| HOFFMAN CONSTRUCTION COMPANY | $775.00000 | 9.000 | EACH | | $6,975.00 |
| JAMES CAPE AND SONS COMPANY | $775.00000 | 9.000 | EACH | | $6,975.00 |
| PEMBER COMPANIES, INC. | $801.74000 | 9.000 | EACH | | $7,215.66 |
| 1670 | 657.0420 | | TRAFFIC SIGNAL STANDARDS ALUMINUM 13-FT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $256.00000 | 16.000 | EACH | | $4,096.00 |
| MCCABE CONSTRUCTION, INC. | $256.00000 | 16.000 | EACH | | $4,096.00 |
| HOFFMAN CONSTRUCTION COMPANY | $256.00000 | 16.000 | EACH | | $4,096.00 |
| JAMES CAPE AND SONS COMPANY | $256.00000 | 16.000 | EACH | | $4,096.00 |
| PEMBER COMPANIES, INC. | $264.83000 | 16.000 | EACH | | $4,237.28 |
| 1680 | 657.0425 | | TRAFFIC SIGNAL STANDARDS ALUMINUM 15-FT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $271.00000 | 2.000 | EACH | | $542.00 |
| MCCABE CONSTRUCTION, INC. | $271.00000 | 2.000 | EACH | | $542.00 |
| HOFFMAN CONSTRUCTION COMPANY | $271.00000 | 2.000 | EACH | | $542.00 |
| JAMES CAPE AND SONS COMPANY | $271.00000 | 2.000 | EACH | | $542.00 |
| PEMBER COMPANIES, INC. | $280.35000 | 2.000 | EACH | | $560.70 |
| 1690 | 657.0430 | | TRAFFIC SIGNAL STANDARDS ALUMINUM 10-FT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $239.00000 | 1.000 | EACH | | $239.00 |
| MCCABE CONSTRUCTION, INC. | $239.00000 | 1.000 | EACH | | $239.00 |
| HOFFMAN CONSTRUCTION COMPANY | $239.00000 | 1.000 | EACH | | $239.00 |
| JAMES CAPE AND SONS COMPANY | $239.00000 | 1.000 | EACH | | $239.00 |
| PEMBER COMPANIES, INC. | $247.25000 | 1.000 | EACH | | $247.25 |
| 1700 | 657.0595.S | | TROMBONE ARMS (LENGTH) 01. 12-FOOT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $629.00000 | 1.000 | EACH | | $629.00 |
| MCCABE CONSTRUCTION, INC. | $629.00000 | 1.000 | EACH | | $629.00 |
| HOFFMAN CONSTRUCTION COMPANY | $629.00000 | 1.000 | EACH | | $629.00 |
| JAMES CAPE AND SONS COMPANY | $629.00000 | 1.000 | EACH | | $629.00 |
| PEMBER COMPANIES, INC. | $650.70000 | 1.000 | EACH | | $650.70 |
| 1710 | 657.0595.S | | TROMBONE ARMS (LENGTH) 02. 20-FOOT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $779.00000 | 6.000 | EACH | | $4,674.00 |
| MCCABE CONSTRUCTION, INC. | $779.00000 | 6.000 | EACH | | $4,674.00 |
| HOFFMAN CONSTRUCTION COMPANY | $779.00000 | 6.000 | EACH | | $4,674.00 |
| JAMES CAPE AND SONS COMPANY | $779.00000 | 6.000 | EACH | | $4,674.00 |
| PEMBER COMPANIES, INC. | $805.88000 | 6.000 | EACH | | $4,835.28 |
| 1720 | 657.0595.S | | TROMBONE ARMS (LENGTH) 03. 25-FOOT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,013.00000 | 2.000 | EACH | | $2,026.00 |
| MCCABE CONSTRUCTION, INC. | $1,013.00000 | 2.000 | EACH | | $2,026.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,013.00000 | 2.000 | EACH | | $2,026.00 |
| JAMES CAPE AND SONS COMPANY | $1,013.00000 | 2.000 | EACH | | $2,026.00 |
| PEMBER COMPANIES, INC. | $1,047.95000 | 2.000 | EACH | | $2,095.90 |
| 1730 | 657.0615 | | LUMINAIRE ARMS SINGLE MEMBER 4 1/2-INCH CLAMP 8-FT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $134.00000 | 10.000 | EACH | | $1,340.00 |
| MCCABE CONSTRUCTION, INC. | $134.00000 | 10.000 | EACH | | $1,340.00 |
| HOFFMAN CONSTRUCTION COMPANY | $134.00000 | 10.000 | EACH | | $1,340.00 |
| JAMES CAPE AND SONS COMPANY | $134.00000 | 10.000 | EACH | | $1,340.00 |
| PEMBER COMPANIES, INC. | $138.62000 | 10.000 | EACH | | $1,386.20 |
| 1740 | 657.0710 | | LUMINAIRE ARMS TRUSS TYPE 4 1/2-INCH CLAMP 12-FT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $204.00000 | 10.000 | EACH | | $2,040.00 |
| MCCABE CONSTRUCTION, INC. | $204.00000 | 10.000 | EACH | | $2,040.00 |
| HOFFMAN CONSTRUCTION COMPANY | $204.00000 | 10.000 | EACH | | $2,040.00 |
| JAMES CAPE AND SONS COMPANY | $204.00000 | 10.000 | EACH | | $2,040.00 |
| PEMBER COMPANIES, INC. | $211.04000 | 10.000 | EACH | | $2,110.40 |
| 1750 | 658.0190.S | | TRAFFIC SIGNAL FACE - LED STATE FURNISHED | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $173.00000 | 38.000 | EACH | | $6,574.00 |
| MCCABE CONSTRUCTION, INC. | $173.00000 | 38.000 | EACH | | $6,574.00 |
| HOFFMAN CONSTRUCTION COMPANY | $173.00000 | 38.000 | EACH | | $6,574.00 |
| JAMES CAPE AND SONS COMPANY | $173.00000 | 38.000 | EACH | | $6,574.00 |
| PEMBER COMPANIES, INC. | $178.97000 | 38.000 | EACH | | $6,800.86 |
| 1760 | 658.0215 | | BACKPLATES SIGNAL FACE 3 SECTION 12-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.00000 | 15.000 | EACH | | $15.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 15.000 | EACH | | $15.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 15.000 | EACH | | $15.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 15.000 | EACH | | $15.00 |
| PEMBER COMPANIES, INC. | $1.03000 | 15.000 | EACH | | $15.45 |
| 1770 | 658.0220 | | BACKPLATES SIGNAL FACE 4 SECTION 12-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.00000 | 3.000 | EACH | | $3.00 |
| MCCABE CONSTRUCTION, INC. | $1.00000 | 3.000 | EACH | | $3.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1.00000 | 3.000 | EACH | | $3.00 |
| JAMES CAPE AND SONS COMPANY | $1.00000 | 3.000 | EACH | | $3.00 |
| PEMBER COMPANIES, INC. | $1.03000 | 3.000 | EACH | | $3.09 |
| 1780 | 658.0420.S | | PEDESTRIAN SIGNAL FACE - LED STATE FURNISHED | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $67.00000 | 4.000 | EACH | | $268.00 |
| MCCABE CONSTRUCTION, INC. | $67.00000 | 4.000 | EACH | | $268.00 |
| HOFFMAN CONSTRUCTION COMPANY | $67.00000 | 4.000 | EACH | | $268.00 |
| JAMES CAPE AND SONS COMPANY | $67.00000 | 4.000 | EACH | | $268.00 |
| PEMBER COMPANIES, INC. | $69.31000 | 4.000 | EACH | | $277.24 |
| 1790 | 658.0500 | | PEDESTRIAN PUSH BUTTONS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $95.00000 | 6.000 | EACH | | $570.00 |
| MCCABE CONSTRUCTION, INC. | $95.00000 | 6.000 | EACH | | $570.00 |
| HOFFMAN CONSTRUCTION COMPANY | $95.00000 | 6.000 | EACH | | $570.00 |
| JAMES CAPE AND SONS COMPANY | $95.00000 | 6.000 | EACH | | $570.00 |
| PEMBER COMPANIES, INC. | $98.28000 | 6.000 | EACH | | $589.68 |
| 1800 | 658.5069 | | SIGNAL MOUNTING HARDWARE (LOCATION) 01. 7255-02-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $851.00000 | 1.000 | LS | | $851.00 |
| MCCABE CONSTRUCTION, INC. | $851.00000 | 1.000 | LS | | $851.00 |
| HOFFMAN CONSTRUCTION COMPANY | $851.00000 | 1.000 | LS | | $851.00 |
| JAMES CAPE AND SONS COMPANY | $851.00000 | 1.000 | LS | | $851.00 |
| PEMBER COMPANIES, INC. | $880.36000 | 1.000 | LS | | $880.36 |
| 1810 | 658.5069 | | SIGNAL MOUNTING HARDWARE (LOCATION) 02. 8610-01-70 | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1,010.00000 | 1.000 | LS | | $1,010.00 |
| MCCABE CONSTRUCTION, INC. | $1,010.00000 | 1.000 | LS | | $1,010.00 |
| HOFFMAN CONSTRUCTION COMPANY | $1,010.00000 | 1.000 | LS | | $1,010.00 |
| JAMES CAPE AND SONS COMPANY | $1,010.00000 | 1.000 | LS | | $1,010.00 |
| PEMBER COMPANIES, INC. | $1,044.84000 | 1.000 | LS | | $1,044.84 |
| 1820 | 659.0115 | | LUMINAIRES UTILITY HPS 150 WATTS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $261.00000 | 12.000 | EACH | | $3,132.00 |
| MCCABE CONSTRUCTION, INC. | $261.00000 | 12.000 | EACH | | $3,132.00 |
| HOFFMAN CONSTRUCTION COMPANY | $261.00000 | 12.000 | EACH | | $3,132.00 |
| JAMES CAPE AND SONS COMPANY | $261.00000 | 12.000 | EACH | | $3,132.00 |
| PEMBER COMPANIES, INC. | $270.00000 | 12.000 | EACH | | $3,240.00 |
| 1830 | 659.0125 | | LUMINAIRES UTILITY HPS 250 WATTS | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $267.00000 | 8.000 | EACH | | $2,136.00 |
| MCCABE CONSTRUCTION, INC. | $267.00000 | 8.000 | EACH | | $2,136.00 |
| HOFFMAN CONSTRUCTION COMPANY | $267.00000 | 8.000 | EACH | | $2,136.00 |
| JAMES CAPE AND SONS COMPANY | $267.00000 | 8.000 | EACH | | $2,136.00 |
| PEMBER COMPANIES, INC. | $276.21000 | 8.000 | EACH | | $2,209.68 |
| 1840 | 661.0200 | | TEMPORARY TRAFFIC SIGNALS FOR INTERSECTIONS (LOCATION) 01. WOODWARD AVENUE INTERSECTION | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $21,449.00000 | 1.000 | LS | | $21,449.00 |
| MCCABE CONSTRUCTION, INC. | $21,449.00000 | 1.000 | LS | | $21,449.00 |
| HOFFMAN CONSTRUCTION COMPANY | $21,449.00000 | 1.000 | LS | | $21,449.00 |
| JAMES CAPE AND SONS COMPANY | $21,449.00000 | 1.000 | LS | | $21,449.00 |
| PEMBER COMPANIES, INC. | $22,188.95000 | 1.000 | LS | | $22,188.95 |
| 1850 | 690.0100 | | SAWING EXISTING PAVEMENT | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $1.50000 | 2,478.000 | LF | | $3,717.00 |
| MCCABE CONSTRUCTION, INC. | $1.55000 | 2,478.000 | LF | | $3,840.90 |
| HOFFMAN CONSTRUCTION COMPANY | $0.95000 | 2,478.000 | LF | | $2,354.10 |
| JAMES CAPE AND SONS COMPANY | $0.95000 | 2,478.000 | LF | | $2,354.10 |
| PEMBER COMPANIES, INC. | $2.07000 | 2,478.000 | LF | | $5,129.46 |
| 1860 | 690.0200 | | SAWING CONCRETE PAVEMENT FULL DEPTH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $2.75000 | 4,515.000 | LF | | $12,416.25 |
| MCCABE CONSTRUCTION, INC. | $2.75000 | 4,515.000 | LF | | $12,416.25 |
| HOFFMAN CONSTRUCTION COMPANY | $2.15000 | 4,515.000 | LF | | $9,707.25 |
| JAMES CAPE AND SONS COMPANY | $2.15000 | 4,515.000 | LF | | $9,707.25 |
| PEMBER COMPANIES, INC. | $3.06000 | 4,515.000 | LF | | $13,815.90 |
| 1870 | ASP.1T0A | | ON-THE-JOB TRAINING APPRENTICE AT $5.00/HR | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $5.00000 | 200.000 | HRS | | $1,000.00 |
| MCCABE CONSTRUCTION, INC. | $5.00000 | 200.000 | HRS | | $1,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $5.00000 | 200.000 | HRS | | $1,000.00 |
| JAMES CAPE AND SONS COMPANY | $5.00000 | 200.000 | HRS | | $1,000.00 |
| PEMBER COMPANIES, INC. | $5.00000 | 200.000 | HRS | | $1,000.00 |
| 1880 | ASP.1T0G | | ON-THE-JOB TRAINING GRADUATE AT $5.00/HR | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $5.00000 | 1,000.000 | HRS | | $5,000.00 |
| MCCABE CONSTRUCTION, INC. | $5.00000 | 1,000.000 | HRS | | $5,000.00 |
| HOFFMAN CONSTRUCTION COMPANY | $5.00000 | 1,000.000 | HRS | | $5,000.00 |
| JAMES CAPE AND SONS COMPANY | $5.00000 | 1,000.000 | HRS | | $5,000.00 |
| PEMBER COMPANIES, INC. | $5.00000 | 1,000.000 | HRS | | $5,000.00 |
| 1890 | SPV.0060 | | SPECIAL 01. ADJUSTING WATER VALVE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $180.00000 | 1.000 | EACH | | $180.00 |
| MCCABE CONSTRUCTION, INC. | $100.00000 | 1.000 | EACH | | $100.00 |
| HOFFMAN CONSTRUCTION COMPANY | $500.00000 | 1.000 | EACH | | $500.00 |
| JAMES CAPE AND SONS COMPANY | $75.00000 | 1.000 | EACH | | $75.00 |
| PEMBER COMPANIES, INC. | $227.89000 | 1.000 | EACH | | $227.89 |
| 1900 | SPV.0060 | | SPECIAL 02. INLET COVER | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $320.00000 | 2.000 | EACH | | $640.00 |
| MCCABE CONSTRUCTION, INC. | $295.00000 | 2.000 | EACH | | $590.00 |
| HOFFMAN CONSTRUCTION COMPANY | $500.00000 | 2.000 | EACH | | $1,000.00 |
| JAMES CAPE AND SONS COMPANY | $800.00000 | 2.000 | EACH | | $1,600.00 |
| PEMBER COMPANIES, INC. | $341.14000 | 2.000 | EACH | | $682.28 |
| 1910 | SPV.0060 | | SPECIAL 03. FRENCH DRAIN | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $3,600.00000 | 2.000 | EACH | | $7,200.00 |
| MCCABE CONSTRUCTION, INC. | $6,770.00000 | 2.000 | EACH | | $13,540.00 |
| HOFFMAN CONSTRUCTION COMPANY | $4,000.00000 | 2.000 | EACH | | $8,000.00 |
| JAMES CAPE AND SONS COMPANY | $5,000.00000 | 2.000 | EACH | | $10,000.00 |
| PEMBER COMPANIES, INC. | $11,955.45000 | 2.000 | EACH | | $23,910.90 |
| 1920 | SPV.0090 | | SPECIAL 01. PAVEMENT MARKING YIELD BAR EPOXY 18-INCH | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $10.00000 | 33.000 | LF | | $330.00 |
| MCCABE CONSTRUCTION, INC. | $6.00000 | 33.000 | LF | | $198.00 |
| HOFFMAN CONSTRUCTION COMPANY | $6.00000 | 33.000 | LF | | $198.00 |
| JAMES CAPE AND SONS COMPANY | $10.00000 | 33.000 | LF | | $330.00 |
| PEMBER COMPANIES, INC. | $10.34000 | 33.000 | LF | | $341.22 |
| 1930 | SPV.0090 | | SPECIAL 02. SAW CUTS FOR LOOP DETECTOR WIRE | BidPrice | Quantity | ExtAmount |
| A-1 EXCAVATING INC. | $8.00000 | 257.000 | LF | | $2,056.00 |
| MCCABE CONSTRUCTION, INC. | $8.00000 | 257.000 | LF | | $2,056.00 |
| HOFFMAN CONSTRUCTION COMPANY | $8.00000 | 257.000 | LF | | $2,056.00 |
| JAMES CAPE AND SONS COMPANY | $8.00000 | 257.000 | LF | | $2,056.00 |
| PEMBER COMPANIES, INC. | $8.28000 | 257.000 | LF | | $2,127.96 |